Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2024 |
Principal Product | Metal heat treating |
NAICS | 332811 - Metal Heat Treating |
SIC | 3398 - Metal Heat Treating |
Sales | $10,000,000-$50,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 75,600 |
Annual Production | 12,000,000 Pounds |
Production Hrs. Annual | 6,624 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $215,273 | 4,535,352 | kWh | $0.05 |
Electricity Demand | $201,431 | 16,803 | kW-months/year | $11.99 |
Electricity Fees | $13,288 | - | $ | - |
Natural Gas | $703,797 | 100,210 | MMBtu | $7.02 |
TOTAL ENERGY COSTS | $1,133,789 | |||
RECOMMENDED SAVINGS* | $45,735 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $40,720 Cost: $77,840 |
- | - | $40,720 | 4,040 | - | - |
- - kWh |
$40,720 4,040 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,190 Cost: $2,260 |
$1,350 | 28,670 | $780 | 78 | $60 | - |
$1,350 28,670 kWh |
$780 78 kW-months/year |
$60 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,515 Cost: - |
$1,020 | 21,640 | $495 | 49 | - | - |
$1,020 21,640 kWh |
$495 49 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,310 Cost: - |
$1,310 | 27,920 | - | - | - | - |
$1,310 27,920 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $45,735 Cost: $80,100 |
$3,680 | 78,230 | $41,995 | 4,167 | $60 | - | $3,680 78,230 kWh |
$41,995 4,167 kW-months/year |
$60 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Ancillary Material Cost | Electricity Usage | Electricity Demand | Ancillary Material Cost |