Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Texas A&M, College Station |
---|---|
Assessment Year | 2025 |
Principal Product | Rolled Steel |
NAICS | 331221 - Rolled Steel Shape Manufacturing |
SIC | 3316 - Cold Finishing Of Steel Shapes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 127,500 |
Annual Production | 50,000 Tons |
Production Hrs. Annual | 1,520 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $35,207 | 625,920 | kWh | $0.06 |
Electricity Demand | $43,394 | 4,950 | kW-months/year | $8.77 |
Electricity Fees | $8,030 | - | $ | - |
Natural Gas | $380 | 1 | MMBtu | $379.57 |
TOTAL ENERGY COSTS | $87,010 | |||
RECOMMENDED SAVINGS* | $259,760 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $213,909 Cost: $2,311,826 |
$213,909 | 3,819,815 | - | - | - | - | - | - |
$213,909 3,819,815 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7273 INSTALL DESICCANT HUMIDITY CONTROL SYSTEM |
Savings: $23,487 Cost: $32,590 |
$15 | 267 | - | - | - | - | $23,472 | - |
$15 267 kWh |
- - kW-months/year |
- - $ |
$23,472 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $8,260 Cost: $15,000 |
- | - | - | - | $8,260 | - | - | - |
- - kWh |
- - kW-months/year |
$8,260 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $6,940 Cost: $16,200 |
- | - | $6,940 | 792 | - | - | - | - |
- - kWh |
$6,940 792 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,804 Cost: $29,010 |
$2,695 | 50,815 | $1,450 | 165 | $1,659 | - | - | - |
$2,695 50,815 kWh |
$1,450 165 kW-months/year |
$1,659 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,360 Cost: $10,180 |
$1,360 | 25,700 | - | - | - | - | - | - |
$1,360 25,700 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $259,760 Cost: $2,414,806 |
$217,979 | 3,896,597 | $8,390 | 957 | $9,919 | - | $23,472 | - | $217,979 3,896,597 kWh |
$8,390 957 kW-months/year |
$9,919 - $ |
$23,472 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost |