Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Arkansas |
---|---|
Assessment Year | 1993 |
Principal Product | Graphite Electrodes |
NAICS | n/a |
SIC | 3624 - Carbon And Graphite Products |
Sales | $5,000,000-$10,000,000 |
# of Employees | 94 |
Plant Area (Sq.Ft.) | 108,717 |
Annual Production | 4,500 Tons |
Production Hrs. Annual | 2,080 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,055,064 | 20,121,044 | kWh | $0.05 |
Natural Gas | $461,974 | 187,519 | MMBtu | $2.46 |
TOTAL ENERGY COSTS | $1,517,038 | |||
RECOMMENDED SAVINGS* | $13,837 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,098 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,244 Cost: $230 |
$2,244 | 42,790 | - | - |
$2,244 42,790 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,622 Cost: $620 |
$7,622 | 145,369 | - | - |
$7,622 145,369 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $1,739 Cost: $600 |
$1,739 | 33,118 | - | - |
$1,739 33,118 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $1,845 Cost: $475 |
- | - | $1,845 | 750 |
- - kWh |
$1,845 750 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $387 Cost: $1,000 |
- | - | $387 | 542 |
- - kWh |
$387 542 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,837 Cost: $2,925 |
$11,605 | 221,277 | $2,232 | 1,292 | $11,605 221,277 kWh |
$2,232 1,292 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,098 Cost: $2,325 |
$9,866 | 188,159 | $2,232 | 1,292 | $9,866 188,159 kWh |
$2,232 1,292 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |