IAC Assessment: AR0140
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AR0140
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Arkansas
Assessment Year 1998
Principal Product Hoist and Related Equipment
NAICS n/a
SIC 3536 - Hoists, Cranes, And Monorails
Sales $50,000,000-$100,000,000
# of Employees 315
Plant Area (Sq.Ft.) 225,000
Annual Production 11,000 Pieces
Production Hrs. Annual 4,000
Location (State) AR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $229,428 7,076,202 kWh $0.03
Electricity Demand $227,699 17,114 kW-months/year $13.30
Natural Gas $83,108 20,575 MMBtu $4.04
TOTAL ENERGY COSTS $600,683
RECOMMENDED SAVINGS* $249,050 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Product Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Product
$ kWh $ kW-months/year $ MMBtu $ gal $ lb $ $ $ $
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$33,786
Cost:
$22,860
- - $33,786 2,541 - - - - - - - - - - -
-
kWh
$33,786
2,541
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,967
Cost:
$250
$876 27,257 $1,091 82 - - - - - - - - - - $876
27,257
kWh
$1,091
82
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,420
Cost:
$130
$1,077 33,705 $1,343 101 - - - - - - - - - - $1,077
33,705
kWh
$1,343
101
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
04: 2.2426 USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR Savings:
$3,592
Cost:
$3,260
$3,592 213,658 - - - - - - - - - - - - $3,592
213,658
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$499
Cost:
$279
$459 14,361 - - $40 10 - - - - - - - - $459
14,361
kWh
-
-
kW-months/year
$40
10
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
06: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$13,190
Cost:
$8,000
$(-179) (-2,638) - - - - - - $13,369 432,000 - - - - $(-179)
(-2,638)
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$13,369
432,000
lb
-
-
$
-
-
$
07: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$46,527
Cost:
$1,000
- - - - - - $42,253 2,523 - - $2,063 - $2,211 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$42,253
2,523
gal
-
-
lb
$2,063
-
$
$2,211
-
$
08: 3.1192 REDUCE SCRAP PRODUCTION Savings:
$14,997
Cost:
$18,800
$(-762) (-10,551) - - $(-3,151) (-780) $19,950 51,000 - - $(-1,040) - - - $(-762)
(-10,551)
kWh
-
-
kW-months/year
$(-3,151)
(-780)
MMBtu
$19,950
51,000
gal
-
-
lb
$(-1,040)
-
$
-
-
$
09: 4.423 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$66,072
Cost:
$3,200
- - - - - - - - - - - - $66,072 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
$66,072
-
$
10: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$66,000
Cost:
$1,280
- - - - - - - - - - - - $66,000 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
$66,000
-
$
TOTAL RECOMMENDED Savings:
$249,050
Cost:
$59,059
$5,063 275,792 $36,220 2,724 $(-3,111) (-770) $62,203 53,523 $13,369 432,000 $1,023 - $134,283 - $5,063
275,792
kWh
$36,220
2,724
kW-months/year
$(-3,111)
(-770)
MMBtu
$62,203
53,523
gal
$13,369
432,000
lb
$1,023
-
$
$134,283
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Product Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Primary Product