Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Arkansas |
---|---|
Assessment Year | 2000 |
Principal Product | Steel Pipe Coupling |
NAICS | n/a |
SIC | 3498 - Fabricated Pipe And Fittings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 175,000 |
Annual Production | 25,000,000 Pounds |
Production Hrs. Annual | 5,616 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $160,822 | 5,592,907 | kWh | $0.03 |
Electricity Demand | $157,918 | 15,689 | kW-months/year | $10.07 |
Natural Gas | $41,359 | 8,169 | MMBtu | $5.06 |
TOTAL ENERGY COSTS | $368,202 | |||
RECOMMENDED SAVINGS* | $516,484 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $19,005 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Primary Product | By-product Production | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Primary Product | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,559 Cost: $260 |
$1,534 | 53,048 | $1,025 | 102 | - | - | - | - | - | - | - | - |
$1,534 53,048 kWh |
$1,025 102 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $6,930 Cost: - |
- | - | $6,930 | 688 | - | - | - | - | - | - | - | - |
- - kWh |
$6,930 688 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2221 USE IMMERSION HEATING IN TANKS, MELTING POTS, ETC |
Savings: $16,446 Cost: $15,663 |
$2,419 | 83,529 | $9,663 | 960 | - | - | $4,364 | - | - | - | - | - |
$2,419 83,529 kWh |
$9,663 960 kW-months/year |
- - lb |
$4,364 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $768 Cost: $300 |
$419 | 14,361 | $349 | 35 | - | - | - | - | - | - | - | - |
$419 14,361 kWh |
$349 35 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $3,764 Cost: - |
- | - | - | - | $3,764 | 2 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,764 2 lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS |
Savings: $21,267 Cost: $59,881 |
- | - | - | - | - | - | - | - | $21,267 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
$21,267 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $464,750 Cost: $385,000 |
- | - | - | - | - | - | - | - | - | - | $464,750 | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
$464,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $516,484 Cost: $461,104 |
$4,372 | 150,938 | $17,967 | 1,785 | $3,764 | 2 | $4,364 | - | $21,267 | - | $464,750 | - | $4,372 150,938 kWh |
$17,967 1,785 kW-months/year |
$3,764 2 lb |
$4,364 - $ |
$21,267 - $ |
$464,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $19,005 Cost: $15,923 |
$3,953 | 136,577 | $10,688 | 1,062 | - | - | $4,364 | - | - | - | - | - | $3,953 136,577 kWh |
$10,688 1,062 kW-months/year |
- - lb |
$4,364 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Primary Product | By-product Production | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Primary Product | By-product Production |