IAC Assessment: AS0178
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0178
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 1996
Principal Product Continuous Buisness Forms
NAICS n/a
SIC 2761 - Manifold Business Forms
Sales $5,000,000-$10,000,000
# of Employees 93
Plant Area (Sq.Ft.) 30,000
Annual Production 2,500 Tons
Production Hrs. Annual 6,120
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $134,431 1,778,136 kWh $0.08
Electricity Demand $8,181 4,194 kW-months/year $1.95
TOTAL ENERGY COSTS $147,032
RECOMMENDED SAVINGS* $41,484 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $24,567
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)
$ kWh $ kW-months/year $ lb
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$224
Cost:
-
$213 2,931 $11 6 - - $213
2,931
kWh
$11
6
kW-months/year
-
-
lb
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,169
Cost:
-
$1,108 14,654 $61 31 - - $1,108
14,654
kWh
$61
31
kW-months/year
-
-
lb
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,213
Cost:
$40
$2,106 27,843 $107 55 - - $2,106
27,843
kWh
$107
55
kW-months/year
-
-
lb
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$11,756
Cost:
$300
$11,190 148,007 $566 290 - - $11,190
148,007
kWh
$566
290
kW-months/year
-
-
lb
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$144
Cost:
$240
$139 1,758 $5 3 - - $139
1,758
kWh
$5
3
kW-months/year
-
-
lb
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$2,076
Cost:
$975
$2,076 27,550 - - - - $2,076
27,550
kWh
-
-
kW-months/year
-
-
lb
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$15,920
Cost:
$18,749
$15,321 202,521 $599 307 - - $15,321
202,521
kWh
$599
307
kW-months/year
-
-
lb
08: 2.7314 REDUCE VENTILATION AIR Savings:
$2,059
Cost:
$980
$1,805 24,033 $254 130 - - $1,805
24,033
kWh
$254
130
kW-months/year
-
-
lb
09: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT Savings:
$1,510
Cost:
-
$1,510 19,930 - - - - $1,510
19,930
kWh
-
-
kW-months/year
-
-
lb
10: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$2,212
Cost:
$4,000
$1,938 25,791 $274 140 - - $1,938
25,791
kWh
$274
140
kW-months/year
-
-
lb
11: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$746
Cost:
$1,600
$746 9,965 - - - - $746
9,965
kWh
-
-
kW-months/year
-
-
lb
12: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE Savings:
$1,455
Cost:
-
- - - - $1,455 425 -
-
kWh
-
-
kW-months/year
$1,455
425
lb
TOTAL RECOMMENDED Savings:
$41,484
Cost:
$26,884
$38,152 504,983 $1,877 962 $1,455 425 $38,152
504,983
kWh
$1,877
962
kW-months/year
$1,455
425
lb
TOTAL IMPLEMENTED Savings:
$24,567
Cost:
$19,764
$22,334 295,429 $778 399 $1,455 425 $22,334
295,429
kWh
$778
399
kW-months/year
$1,455
425
lb
Savings
Cost
$ kWh $ kW-months/year $ lb
Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)