Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 1996 |
Principal Product | Antenna Systems and Related Equipment |
NAICS | n/a |
SIC | 3662 - |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 170,000 |
Annual Production | 24,000 Pieces |
Production Hrs. Annual | 2,525 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $216,997 | 2,702,227 | kWh | $0.08 |
Electricity Demand | $19,678 | 10,174 | kW-months/year | $1.93 |
TOTAL ENERGY COSTS | $236,675 | |||
RECOMMENDED SAVINGS* | $109,927 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $27,354 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | By-product Production | Electricity Usage | Electricity Demand | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $13,771 Cost: $38,500 |
$12,422 | 234,760 | $1,349 | 683 | - | - |
$12,422 234,760 kWh |
$1,349 683 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7228 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM |
Savings: $6,617 Cost: $13,200 |
$6,617 | 121,336 | - | - | - | - |
$6,617 121,336 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $872 Cost: $975 |
$872 | 16,413 | - | - | - | - |
$872 16,413 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,057 Cost: $1,120 |
$926 | 17,585 | $131 | 66 | - | - |
$926 17,585 kWh |
$131 66 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $2,337 Cost: - |
$2,047 | 38,687 | $290 | 147 | - | - |
$2,047 38,687 kWh |
$290 147 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $12,177 Cost: - |
$10,665 | 201,641 | $1,512 | 766 | - | - |
$10,665 201,641 kWh |
$1,512 766 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $4,031 Cost: - |
$3,530 | 66,823 | $501 | 253 | - | - |
$3,530 66,823 kWh |
$501 253 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $218 Cost: - |
$218 | 4,396 | - | - | - | - |
$218 4,396 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7314 REDUCE VENTILATION AIR |
Savings: $263 Cost: $100 |
$263 | 4,982 | - | - | - | - |
$263 4,982 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $900 Cost: - |
- | - | - | - | $900 | - |
- - kWh |
- - kW-months/year |
$900 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.511 EXPAND OPERATIONS INTO UNUSED SPACE |
Savings: $67,684 Cost: $10,000 |
- | - | - | - | $67,684 | - |
- - kWh |
- - kW-months/year |
$67,684 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $109,927 Cost: $63,895 |
$37,560 | 706,623 | $3,783 | 1,915 | $68,584 | - | $37,560 706,623 kWh |
$3,783 1,915 kW-months/year |
$68,584 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $27,354 Cost: $15,395 |
$24,920 | 467,467 | $2,434 | 1,232 | - | - | $24,920 467,467 kWh |
$2,434 1,232 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | By-product Production | Electricity Usage | Electricity Demand | By-product Production |