Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 1998 |
Principal Product | Machinery and Subassemblies for Semiconductor Equipment |
NAICS | n/a |
SIC | 3559 - Special Industry Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 115 |
Plant Area (Sq.Ft.) | 46,000 |
Annual Production | 23,000 Pieces |
Production Hrs. Annual | 4,896 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $114,151 | 2,038,980 | kWh | $0.06 |
Electricity Demand | $10,582 | 3,784 | kW-months/year | $2.80 |
Electricity Fees | $9,776 | - | $ | - |
TOTAL ENERGY COSTS | $134,509 | |||
RECOMMENDED SAVINGS* | $10,607 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $901 Cost: $1,875 |
$901 | 23,154 | - | - | - | - | - | - | - | - |
$901 23,154 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,256 Cost: $16,930 |
$4,623 | 118,406 | $2,633 | 240 | - | - | - | - | - | - |
$4,623 118,406 kWh |
$2,633 240 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $1,014 Cost: $60 |
- | - | - | - | $1,014 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,014 - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.812 APPLY FOR INVESTMENT INCENTIVES |
Savings: $1,436 Cost: $60 |
- | - | - | - | - | - | $1,280 | - | $156 | - |
- - kWh |
- - kW-months/year |
- - lb |
$1,280 - $ |
$156 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,607 Cost: $18,925 |
$5,524 | 141,560 | $2,633 | 240 | $1,014 | - | $1,280 | - | $156 | - | $5,524 141,560 kWh |
$2,633 240 kW-months/year |
$1,014 - lb |
$1,280 - $ |
$156 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost |