IAC Assessment: AS0256
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0256
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 1999
Principal Product Aircraft
NAICS n/a
SIC 3721 - Aircraft
Sales $50,000,000-$100,000,000
# of Employees 500
Plant Area (Sq.Ft.) 260,067
Annual Production 42 Pieces
Production Hrs. Annual 8,760
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $281,857 3,612,251 kWh $0.08
Electricity Demand $49,494 8,188 kW-months/year $6.04
Electricity Fees $17,381 - $ -
Natural Gas $112,559 17,409 MMBtu $6.47
TOTAL ENERGY COSTS $483,098
RECOMMENDED SAVINGS* $169,995 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$6,547
Cost:
$4,500
$5,724 85,873 $823 176 - - - - - - $5,724
85,873
kWh
$823
176
kW-months/year
-
-
$
-
-
$
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$9,763
Cost:
$2,550
$9,262 138,921 $501 71 - - - - - - $9,262
138,921
kWh
$501
71
kW-months/year
-
-
$
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,273
Cost:
$1,496
$741 11,137 $102 15 $217 - - - $213 - $741
11,137
kWh
$102
15
kW-months/year
$217
-
$
-
-
$
$213
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$13,376
Cost:
$14,720
$11,751 198,124 $1,625 262 - - - - - - $11,751
198,124
kWh
$1,625
262
kW-months/year
-
-
$
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$29,301
Cost:
$22,500
$25,458 381,887 $3,843 549 - - - - - - $25,458
381,887
kWh
$3,843
549
kW-months/year
-
-
$
-
-
$
-
-
$
06: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$4,880
Cost:
$4,220
$4,880 73,271 - - - - - - - - $4,880
73,271
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
07: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS Savings:
$22,194
Cost:
$2,804
$22,194 332,943 - - - - - - - - $22,194
332,943
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
08: 2.3512 DE-ENERGIZE EXCESS TRANSFORMER CAPACITY Savings:
$23,808
Cost:
$59,466
$8,238 123,681 - - - - - - $15,570 - $8,238
123,681
kWh
-
-
kW-months/year
-
-
$
-
-
$
$15,570
-
$
09: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$3,644
Cost:
$120
- - - - - - $3,644 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$3,644
-
$
-
-
$
10: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$3,507
Cost:
$30
- - - - - - $3,507 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$3,507
-
$
-
-
$
11: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$51,702
Cost:
$240
- - - - - - $51,702 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$51,702
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$169,995
Cost:
$112,646
$88,248 1,345,837 $6,894 1,073 $217 - $58,853 - $15,783 - $88,248
1,345,837
kWh
$6,894
1,073
kW-months/year
$217
-
$
$58,853
-
$
$15,783
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost