Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 1999 |
Principal Product | Windows and Doors |
NAICS | n/a |
SIC | 3231 - Products Of Purchased Glass |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 42,000 |
Annual Production | 1,000 Thousand Feet |
Production Hrs. Annual | 4,352 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $27,507 | 425,264 | kWh | $0.06 |
Electricity Demand | $5,043 | 1,782 | kW-months/year | $2.83 |
Electricity Fees | $2,483 | - | $ | - |
TOTAL ENERGY COSTS | $38,962 | |||
RECOMMENDED SAVINGS* | $40,644 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $2,440 Cost: $3,500 |
$2,136 | 38,394 | $304 | 52 | - | - | - | - | - | - | - | - | - | - |
$2,136 38,394 kWh |
$304 52 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $623 Cost: $1,400 |
$440 | 7,913 | $183 | 32 | - | - | - | - | - | - | - | - | - | - |
$440 7,913 kWh |
$183 32 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $155 Cost: $100 |
$91 | 1,758 | $38 | 7 | - | - | $26 | - | - | - | - | - | - | - |
$91 1,758 kWh |
$38 7 kW-months/year |
- - Tgal |
$26 - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $242 Cost: $240 |
$142 | 2,638 | $15 | 3 | - | - | $45 | - | - | - | $40 | - | - | - |
$142 2,638 kWh |
$15 3 kW-months/year |
- - Tgal |
$45 - $ |
- - $ |
$40 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5217 REUSE / RECYCLE/ SELL PAPER PRODUCTS |
Savings: $2,717 Cost: $120 |
- | - | - | - | - | - | - | - | $2,197 | - | - | - | $520 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
$2,197 - $ |
- - $ |
$520 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $27 Cost: $38 |
- | - | - | - | $27 | 13,100 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$27 13,100 Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.114 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS |
Savings: $34,440 Cost: $1,220 |
$384 | 7,034 | - | - | - | - | $34,056 | - | - | - | - | - | - | - |
$384 7,034 kWh |
- - kW-months/year |
- - Tgal |
$34,056 - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,644 Cost: $6,618 |
$3,193 | 57,737 | $540 | 94 | $27 | 13,100 | $34,127 | - | $2,197 | - | $40 | - | $520 | - | $3,193 57,737 kWh |
$540 94 kW-months/year |
$27 13,100 Tgal |
$34,127 - $ |
$2,197 - $ |
$40 - $ |
$520 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | By-product Production |