IAC Assessment: AS0265
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0265
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 1999
Principal Product Electronic Components
NAICS n/a
SIC 3675 - Electronic Capacitors
Sales $500,000-$1,000,000
# of Employees 15
Plant Area (Sq.Ft.) 30,000
Annual Production 4,700,000 Pieces
Production Hrs. Annual 2,125
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $21,591 210,727 kWh $0.10
Electricity Fees $1,283 - $ -
TOTAL ENERGY COSTS $26,450
RECOMMENDED SAVINGS* $6,516 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ Tgal $ gal $ lb $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,958
Cost:
$7,252
$1,958 19,050 - - - - - - - - - - - - $1,958
19,050
kWh
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$568
Cost:
$1,275
$568 5,569 - - - - - - - - - - - - $568
5,569
kWh
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$337
Cost:
$75
$337 3,224 - - - - - - - - - - - - $337
3,224
kWh
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
04: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$456
Cost:
$60
- - - - - - $456 - - - - - - - -
-
kWh
-
-
Tgal
-
-
gal
$456
-
lb
-
-
$
-
-
$
-
-
$
05: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$1,565
Cost:
$120
- - - - $1,565 - - - - - - - - - -
-
kWh
-
-
Tgal
$1,565
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
06: 4.231 PURCHASE EQUIPMENT INSTEAD OF LEASING Savings:
$1,632
Cost:
$230
- - $(-8) (-3,125) - - - - $(-30) - $1,800 - $(-130) - -
-
kWh
$(-8)
(-3,125)
Tgal
-
-
gal
-
-
lb
$(-30)
-
$
$1,800
-
$
$(-130)
-
$
TOTAL RECOMMENDED Savings:
$6,516
Cost:
$9,012
$2,863 27,843 $(-8) (-3,125) $1,565 - $456 - $(-30) - $1,800 - $(-130) - $2,863
27,843
kWh
$(-8)
(-3,125)
Tgal
$1,565
-
gal
$456
-
lb
$(-30)
-
$
$1,800
-
$
$(-130)
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - - - -
-
kWh
-
-
Tgal
-
-
gal
-
-
lb
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ Tgal $ gal $ lb $ $ $ $ $ $
Electricity Usage Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Water Disposal Other Liquid (haz) Solid Waste (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost