IAC Assessment: AS0267
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0267
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2000
Principal Product Embroidery
NAICS n/a
SIC 2329 - Men's and Boys' Clothing, Not Elsewhere Classified
Sales $10,000,000-$50,000,000
# of Employees 250
Plant Area (Sq.Ft.) 91,000
Annual Production 1,600,000 Pieces
Production Hrs. Annual 6,467
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $123,753 1,353,458 kWh $0.09
Electricity Demand $6,906 5,057 kW-months/year $1.37
Electricity Fees $10,593 - $ -
TOTAL ENERGY COSTS $145,912
RECOMMENDED SAVINGS* $662,082 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$13,649
Cost:
$30,357
$11,813 155,920 $1,836 343 - - - - - - - - $11,813
155,920
kWh
$1,836
343
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$2,547
Cost:
$2,475
$2,292 30,188 $255 48 - - - - - - - - $2,292
30,188
kWh
$255
48
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,204
Cost:
$1,012
$769 10,258 $59 11 - - $210 - - - $166 - $769
10,258
kWh
$59
11
kW-months/year
-
-
$
$210
-
$
-
-
$
$166
-
$
04: 2.7145 INSTALL SKYLIGHTS Savings:
$2,171
Cost:
$1,680
$2,171 28,722 - - - - - - - - - - $2,171
28,722
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
05: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$29,540
Cost:
$31,800
$26,932 355,217 $2,608 486 - - - - - - - - $26,932
355,217
kWh
$2,608
486
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$2,700
Cost:
$60
- - - - - - - - $2,700 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
$2,700
-
$
-
-
$
07: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$1,608
Cost:
$60
- - - - - - - - $1,608 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
$1,608
-
$
-
-
$
08: 4.5120 CONDENSE OPERATION INTO ONE BUILDING Savings:
$604,757
Cost:
$2,250,000
- - $(-1,867) - $21,599 - - - $585,025 - - - -
-
kWh
$(-1,867)
-
kW-months/year
$21,599
-
$
-
-
$
$585,025
-
$
-
-
$
09: 4.2310 PURCHASE EQUIPMENT INSTEAD OF LEASING Savings:
$3,906
Cost:
$12,060
- - - - - - - - $3,906 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
$3,906
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$662,082
Cost:
$2,329,504
$43,977 580,305 $2,891 888 $21,599 - $210 - $593,239 - $166 - $43,977
580,305
kWh
$2,891
888
kW-months/year
$21,599
-
$
$210
-
$
$593,239
-
$
$166
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost