IAC logo
IAC Assessment: AS0309
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0309
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2001
Principal Product Mill work and wood doors
NAICS n/a
SIC 2431 - Millwork
Sales $10,000,000-$50,000,000
# of Employees 48
Plant Area (Sq.Ft.) 26,600
Annual Production 8,000 Units
Production Hrs. Annual 2,151
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $14,099 225,829 kWh $0.06
Electricity Demand $1,980 839 kW-months/year $2.36
Electricity Fees $1,757 - $ -
TOTAL ENERGY COSTS $17,836
RECOMMENDED SAVINGS* $12,827 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $12,805
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Administrative Changes Primary Product Electricity Usage Electricity Demand Administrative Changes Primary Product
$ kWh $ kW-months/year $ $ $ $
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,341
Cost:
$3,800
$1,497 26,543 $844 148 - - - - $1,497
26,543
kWh
$844
148
kW-months/year
-
-
$
-
-
$
02: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$426
Cost:
$480
$426 7,550 - - - - - - $426
7,550
kWh
-
-
kW-months/year
-
-
$
-
-
$
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$305
Cost:
$60
$157 2,788 $148 26 - - - - $157
2,788
kWh
$148
26
kW-months/year
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$962
Cost:
$4,006
$705 12,507 $257 46 - - - - $705
12,507
kWh
$257
46
kW-months/year
-
-
$
-
-
$
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$22
Cost:
$75
$15 260 $7 6 - - - - $15
260
kWh
$7
6
kW-months/year
-
-
$
-
-
$
06: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$585
Cost:
$1,400
$410 7,267 $175 31 - - - - $410
7,267
kWh
$175
31
kW-months/year
-
-
$
-
-
$
07: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$5,413
Cost:
$60
- - - - $5,413 - - - -
-
kWh
-
-
kW-months/year
$5,413
-
$
-
-
$
08: 4.1110 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$2,773
Cost:
$685
- - - - - - $2,773 - -
-
kWh
-
-
kW-months/year
-
-
$
$2,773
-
$
TOTAL RECOMMENDED Savings:
$12,827
Cost:
$10,566
$3,210 56,915 $1,431 257 $5,413 - $2,773 - $3,210
56,915
kWh
$1,431
257
kW-months/year
$5,413
-
$
$2,773
-
$
TOTAL IMPLEMENTED Savings:
$12,805
Cost:
$10,491
$3,195 56,655 $1,424 251 $5,413 - $2,773 - $3,195
56,655
kWh
$1,424
251
kW-months/year
$5,413
-
$
$2,773
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Administrative Changes Primary Product Electricity Usage Electricity Demand Administrative Changes Primary Product