Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2001 |
Principal Product | Wood household furniture |
NAICS | n/a |
SIC | 2511 - Wood Household Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 420 |
Plant Area (Sq.Ft.) | 108,000 |
Annual Production | 460,000 Units |
Production Hrs. Annual | 4,554 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $216,004 | 2,800,729 | kWh | $0.08 |
Electricity Demand | $16,553 | 10,200 | kW-months/year | $1.62 |
Electricity Fees | $16,824 | - | $ | - |
TOTAL ENERGY COSTS | $249,381 | |||
RECOMMENDED SAVINGS* | $126,586 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $77,836 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Administrative Changes | Primary Product | Electricity Usage | Electricity Demand | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $2,092 Cost: $1,500 |
$1,080 | 23,450 | $1,012 | 257 | - | - | - | - |
$1,080 23,450 kWh |
$1,012 257 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $311 Cost: $1,254 |
$163 | 3,561 | $148 | 19 | - | - | - | - |
$163 3,561 kWh |
$148 19 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $44,929 Cost: $31,000 |
$30,946 | 674,356 | $13,983 | 1,777 | - | - | - | - |
$30,946 674,356 kWh |
$13,983 1,777 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $12,661 Cost: $180 |
$8,429 | 183,678 | $4,232 | 538 | - | - | - | - |
$8,429 183,678 kWh |
$4,232 538 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $13,639 Cost: $24,888 |
$9,631 | 209,880 | $4,008 | 510 | - | - | - | - |
$9,631 209,880 kWh |
$4,008 510 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7145 INSTALL SKYLIGHTS |
Savings: $1,042 Cost: $8,108 |
$1,042 | 15,179 | - | - | - | - | - | - |
$1,042 15,179 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $71 Cost: $225 |
$41 | 886 | $30 | 19 | - | - | - | - |
$41 886 kWh |
$30 19 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $2,708 Cost: $735 |
- | - | - | - | - | - | $2,708 | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,708 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $49,133 Cost: $8,028 |
- | - | - | - | $49,133 | - | - | - |
- - kWh |
- - kW-months/year |
$49,133 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $126,586 Cost: $75,918 |
$51,332 | 1,110,990 | $23,413 | 3,120 | $49,133 | - | $2,708 | - | $51,332 1,110,990 kWh |
$23,413 3,120 kW-months/year |
$49,133 - $ |
$2,708 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $77,836 Cost: $35,850 |
$19,303 | 420,569 | $9,400 | 1,324 | $49,133 | - | - | - | $19,303 420,569 kWh |
$9,400 1,324 kW-months/year |
$49,133 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Administrative Changes | Primary Product | Electricity Usage | Electricity Demand | Administrative Changes | Primary Product |