Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Arizona State University |
---|---|
Assessment Year | 2020 |
Principal Product | Treated Wastewater |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | <$500,000 |
# of Employees | 11 |
Plant Area (Sq.Ft.) | 30,000 |
Annual Production | 2,000,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | AZ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $632,133 | 9,156,662 | kWh | $0.07 |
Electricity Demand | $83,560 | 15,989 | kW-months/year | $5.23 |
Electricity Fees | $61,539 | - | $ | - |
TOTAL ENERGY COSTS | $777,232 | |||
RECOMMENDED SAVINGS* | $266,363 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $180,477 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $176,974 Cost: $3,941 |
$163,403 | 2,368,160 | $13,571 | 2,595 | - | - | - | - |
$163,403 2,368,160 kWh |
$13,571 2,595 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8112 COMBINE UTILITY METERS |
Savings: $69,299 Cost: $735 |
$107,959 | - | $(-30,500) | - | $(-8,160) | - | - | - |
$107,959 - kWh |
$(-30,500) - kW-months/year |
$(-8,160) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $16,587 Cost: $9,520 |
$15,066 | 218,353 | $1,521 | 291 | - | - | - | - |
$15,066 218,353 kWh |
$1,521 291 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,757 Cost: $511 |
$1,757 | 25,458 | - | - | - | - | - | - |
$1,757 25,458 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,511 Cost: $2,230 |
$1,323 | 19,167 | $136 | 26 | - | - | $52 | - |
$1,323 19,167 kWh |
$136 26 kW-months/year |
- - $ |
$52 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7272 INSTALL HEAT PIPES / RAISE COOLING SETPOINT |
Savings: $235 Cost: $38 |
$180 | 2,606 | $55 | 10 | - | - | - | - |
$180 2,606 kWh |
$55 10 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $266,363 Cost: $16,975 |
$289,688 | 2,633,744 | $(-15,217) | 2,922 | $(-8,160) | - | $52 | - | $289,688 2,633,744 kWh |
$(-15,217) 2,922 kW-months/year |
$(-8,160) - $ |
$52 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $180,477 Cost: $6,720 |
$166,663 | 2,415,391 | $13,762 | 2,631 | - | - | $52 | - | $166,663 2,415,391 kWh |
$13,762 2,631 kW-months/year |
- - $ |
$52 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost |