IAC Assessment: AS0496
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0496
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2021
Principal Product Treated Wastewater
NAICS 221320 - Sewage Treatment Facilities
SIC 4952 - Sewerage Systems
Sales <$500,000
# of Employees 6
Plant Area (Sq.Ft.) 4,260
Annual Production 511,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $132,646 2,133,000 kWh $0.06
Electricity Demand $57,099 5,076 kW-months/year $11.25
Electricity Fees $18,753 - $ -
TOTAL ENERGY COSTS $208,498
RECOMMENDED SAVINGS* $198,987 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $24,229
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Ancillary Material Cost One-time Revenue or Avoided Cost By-product Production Electricity Usage Electricity Demand Ancillary Material Cost One-time Revenue or Avoided Cost By-product Production
$ kWh $ kW-months/year $ $ $ $ $ $
01: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE Savings:
$174,284
Cost:
$89,232
- - - - $(-221,558) - $80,482 - $315,360 - -
-
kWh
-
-
kW-months/year
$(-221,558)
-
$
$80,482
-
$
$315,360
-
$
02: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT Savings:
$18,309
Cost:
$3,941
$15,193 253,222 $3,116 277 - - - - - - $15,193
253,222
kWh
$3,116
277
kW-months/year
-
-
$
-
-
$
-
-
$
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$2,587
Cost:
$789
$2,059 34,316 $528 47 - - - - - - $2,059
34,316
kWh
$528
47
kW-months/year
-
-
$
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,402
Cost:
$3,920
$1,290 18,329 $328 29 - - $(-216) - - - $1,290
18,329
kWh
$328
29
kW-months/year
-
-
$
$(-216)
-
$
-
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,262
Cost:
$6,259
$756 12,614 $506 45 - - - - - - $756
12,614
kWh
$506
45
kW-months/year
-
-
$
-
-
$
-
-
$
06: 2.7272 INSTALL HEAT PIPES / RAISE COOLING SETPOINT Savings:
$499
Cost:
$35
$324 5,406 $175 16 - - - - - - $324
5,406
kWh
$175
16
kW-months/year
-
-
$
-
-
$
-
-
$
07: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$474
Cost:
$188
$377 6,276 $97 9 - - - - - - $377
6,276
kWh
$97
9
kW-months/year
-
-
$
-
-
$
-
-
$
08: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$170
Cost:
$275
$170 2,836 - - - - - - - - $170
2,836
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$198,987
Cost:
$104,639
$20,169 332,999 $4,750 422 $(-221,558) - $80,266 - $315,360 - $20,169
332,999
kWh
$4,750
422
kW-months/year
$(-221,558)
-
$
$80,266
-
$
$315,360
-
$
TOTAL IMPLEMENTED Savings:
$24,229
Cost:
$15,219
$19,792 326,723 $4,653 414 - - $(-216) - - - $19,792
326,723
kWh
$4,653
414
kW-months/year
-
-
$
$(-216)
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Ancillary Material Cost One-time Revenue or Avoided Cost By-product Production Electricity Usage Electricity Demand Ancillary Material Cost One-time Revenue or Avoided Cost By-product Production