IAC logo
IAC Assessment: AS0498
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0498
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2021
Principal Product Dried Colostrum
NAICS 311514 - Dry, Condensed, and Evaporated Dairy Product Manufacturing
SIC 2023 - Dry, Condensed, Evaporated Products
Sales $10,000,000-$50,000,000
# of Employees 50
Plant Area (Sq.Ft.) 87,000
Annual Production 1 Units
Production Hrs. Annual 8,760
Location (State) AZ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $181,032 4,011,600 kWh $0.05
Electricity Demand $200,288 10,308 kW-months/year $19.43
Electricity Fees $41,520 - $ -
Natural Gas $165,725 44,549 MMBtu $3.72
TOTAL ENERGY COSTS $708,650
RECOMMENDED SAVINGS* $48,440 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $48,440
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.8112 COMBINE UTILITY METERS Savings:
$25,997
Cost:
$1,473
$(-33,107) - $57,673 - $1,431 - - - - - $(-33,107)
-
kWh
$57,673
-
kW-months/year
$1,431
-
$
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$10,073
Cost:
$11,543
$5,712 128,083 $3,396 175 - - - - $965 - $5,712
128,083
kWh
$3,396
175
kW-months/year
-
-
$
-
-
$
$965
-
$
03: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$5,616
Cost:
$453
- - - - - - $5,616 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$5,616
-
$
-
-
$
04: 2.3113 MAKE ICE DURING OFF PEAK HOURS FOR COOLING Savings:
$4,426
Cost:
$15,525
$(-79) (-1,778) $4,505 232 - - - - - - $(-79)
(-1,778)
kWh
$4,505
232
kW-months/year
-
-
$
-
-
$
-
-
$
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$2,328
Cost:
$1,452
$2,328 52,191 - - - - - - - - $2,328
52,191
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$48,440
Cost:
$30,446
$(-25,146) 178,496 $65,574 407 $1,431 - $5,616 - $965 - $(-25,146)
178,496
kWh
$65,574
407
kW-months/year
$1,431
-
$
$5,616
-
$
$965
-
$
TOTAL IMPLEMENTED Savings:
$48,440
Cost:
$30,446
$(-25,146) 178,496 $65,574 407 $1,431 - $5,616 - $965 - $(-25,146)
178,496
kWh
$65,574
407
kW-months/year
$1,431
-
$
$5,616
-
$
$965
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost One-time Revenue or Avoided Cost