IAC logo
IAC Assessment: AS0540
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0540
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2022
Principal Product Water supply and irrigation
NAICS 221320 - Sewage Treatment Facilities
SIC 4941 - Water Supply
Sales $1,000,000-$5,000,000
# of Employees 50
Plant Area (Sq.Ft.) 2,000
Annual Production 600,000 Thousand Gallons
Production Hrs. Annual 8,760
Location (State) NM
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $175,057 1,776,723 kWh $0.10
Electricity Demand $70,791 4,619 kW-months/year $15.33
Electricity Fees $38,745 - $ -
TOTAL ENERGY COSTS $284,593
RECOMMENDED SAVINGS* $22,258 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $12,247
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$9,774
Cost:
$97,049
$9,108 92,466 $666 43 - - - - $9,108
92,466
kWh
$666
43
kW-months/year
-
-
$
-
-
$
02: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$9,085
Cost:
$21
- - - - $9,085 - - - -
-
kWh
-
-
kW-months/year
$9,085
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,767
Cost:
$4,200
$1,414 14,356 $306 20 - - $1,047 - $1,414
14,356
kWh
$306
20
kW-months/year
-
-
$
$1,047
-
$
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$395
Cost:
$1,341
$296 3,008 $99 6 - - - - $296
3,008
kWh
$99
6
kW-months/year
-
-
$
-
-
$
05: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS Savings:
$237
Cost:
$398
$178 1,807 $59 4 - - - - $178
1,807
kWh
$59
4
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$22,258
Cost:
$103,009
$10,996 111,637 $1,130 73 $9,085 - $1,047 - $10,996
111,637
kWh
$1,130
73
kW-months/year
$9,085
-
$
$1,047
-
$
TOTAL IMPLEMENTED Savings:
$12,247
Cost:
$5,562
$1,710 17,364 $405 26 $9,085 - $1,047 - $1,710
17,364
kWh
$405
26
kW-months/year
$9,085
-
$
$1,047
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Ancillary Material Cost