IAC Assessment: AS0542
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: AS0542
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Arizona State University
Assessment Year 2023
Principal Product banking services
NAICS 522110 - Commercial Banking
SIC 6021 - National Commercial Banks
Sales $1,000,000-$5,000,000
# of Employees 250
Plant Area (Sq.Ft.) 71,166
Annual Production 1 Units
Production Hrs. Annual 3,002
Location (State) NM
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $90,520 1,102,560 kWh $0.08
Electricity Demand $29,448 2,677 kW-months/year $11.00
Electricity Fees $10,332 - $ -
Natural Gas $15,866 2,013 MMBtu $7.88
TOTAL ENERGY COSTS $146,166
RECOMMENDED SAVINGS* $25,902 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,554
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost
$ kWh $ kW-months/year $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,466
Cost:
$22,203
$6,546 79,734 $2,800 255 $2,120 - $6,546
79,734
kWh
$2,800
255
kW-months/year
$2,120
-
$
02: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE Savings:
$9,017
Cost:
$19,689
$9,017 109,829 - - - - $9,017
109,829
kWh
-
-
kW-months/year
-
-
$
03: 2.7272 INSTALL HEAT PIPES / RAISE COOLING SETPOINT Savings:
$5,088
Cost:
$71
$2,546 31,006 $2,542 231 - - $2,546
31,006
kWh
$2,542
231
kW-months/year
-
-
$
04: 3.1161 ELIMINATE/REDUCE AN OPERATION Savings:
$331
Cost:
$50
$89 1,080 $242 22 - - $89
1,080
kWh
$242
22
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$25,902
Cost:
$42,013
$18,198 221,649 $5,584 508 $2,120 - $18,198
221,649
kWh
$5,584
508
kW-months/year
$2,120
-
$
TOTAL IMPLEMENTED Savings:
$16,554
Cost:
$22,274
$9,092 110,740 $5,342 486 $2,120 - $9,092
110,740
kWh
$5,342
486
kW-months/year
$2,120
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost