Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Boise State University |
---|---|
Assessment Year | 2014 |
Principal Product | Mining Equipment |
NAICS | 333131 - Mining Machinery and Equipment Manufacturing |
SIC | 3532 - Mining Machinery |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 120,000 |
Annual Production | 172 Pieces |
Production Hrs. Annual | 2,080 |
Location (State) | ID |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $73,260 | 1,126,093 | kWh | $0.07 |
Electricity Demand | $31,637 | 6,296 | kW-months/year | $5.02 |
Natural Gas | $106,231 | 15,181 | MMBtu | $7.00 |
TOTAL ENERGY COSTS | $211,128 | |||
RECOMMENDED SAVINGS* | $34,250 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2111 INSTALL STEAM TRAP |
Savings: $123 Cost: $217 |
$123 | 1,890 | - | - | - | - | - | - |
$123 1,890 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,073 Cost: $15 |
$686 | 10,558 | $387 | 77 | - | - | - | - |
$686 10,558 kWh |
$387 77 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $263 Cost: $168 |
$263 | 4,052 | - | - | - | - | - | - |
$263 4,052 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $464 Cost: $10 |
$464 | 7,139 | - | - | - | - | - | - |
$464 7,139 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $4,302 Cost: $17,525 |
$(-328) | (-5,040) | - | - | $4,630 | 760 | - | - |
$(-328) (-5,040) kWh |
- - kW-months/year |
$4,630 760 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $2,800 Cost: $2,668 |
- | - | - | - | $2,800 | 400 | - | - |
- - kWh |
- - kW-months/year |
$2,800 400 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,179 Cost: $360 |
$1,502 | 23,113 | - | - | - | - | $677 | - |
$1,502 23,113 kWh |
- - kW-months/year |
- - MMBtu |
$677 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,767 Cost: $23,688 |
$1,240 | 19,080 | $527 | 105 | - | - | - | - |
$1,240 19,080 kWh |
$527 105 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $33 Cost: $160 |
$33 | 508 | - | - | - | - | - | - |
$33 508 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $21,246 Cost: $1,547 |
- | - | - | - | $21,246 | 3,036 | - | - |
- - kWh |
- - kW-months/year |
$21,246 3,036 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,250 Cost: $46,358 |
$3,983 | 61,300 | $914 | 182 | $28,676 | 4,196 | $677 | - | $3,983 61,300 kWh |
$914 182 kW-months/year |
$28,676 4,196 MMBtu |
$677 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |