IAC Assessment: BS0089
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BS0089
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Boise State University
Assessment Year 2016
Principal Product Composit Decking and Fencing Material
NAICS 321999 - All Other Miscellaneous Wood Product Manufacturing
SIC 2499 - Wood Products, Nec
Sales $50,000,000-$100,000,000
# of Employees 67
Plant Area (Sq.Ft.) 221,000
Annual Production 60,000,000 Pounds
Production Hrs. Annual 8,760
Location (State) ID
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $685,030 14,651,093 kWh $0.05
Electricity Demand $218,769 39,879 kW-months/year $5.49
Electricity Fees $46,495 - $ -
Natural Gas $106,803 15,279 MMBtu $6.99
TOTAL ENERGY COSTS $1,057,097
RECOMMENDED SAVINGS* $48,694 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Electricity Usage Electricity Demand Electricity Fees
$ kWh $ kW-months/year $ $
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$8,075
Cost:
$353
$6,957 148,774 $1,118 204 - - $6,957
148,774
kWh
$1,118
204
kW-months/year
-
-
$
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$7,566
Cost:
$6,400
$7,407 158,400 $159 29 - - $7,407
158,400
kWh
$159
29
kW-months/year
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,855
Cost:
$654
$1,597 34,184 $258 47 - - $1,597
34,184
kWh
$258
47
kW-months/year
-
-
$
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$1,615
Cost:
$4,480
$1,390 29,734 $225 41 - - $1,390
29,734
kWh
$225
41
kW-months/year
-
-
$
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$3,760
Cost:
$4,580
$3,760 80,417 - - - - $3,760
80,417
kWh
-
-
kW-months/year
-
-
$
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$5,303
Cost:
$1,200
$5,303 113,442 - - - - $5,303
113,442
kWh
-
-
kW-months/year
-
-
$
07: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$15,910
Cost:
$115,903
- - - - $15,910 - -
-
kWh
-
-
kW-months/year
$15,910
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,610
Cost:
$15,011
$3,968 84,866 $642 117 - - $3,968
84,866
kWh
$642
117
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$48,694
Cost:
$148,581
$30,382 649,817 $2,402 438 $15,910 - $30,382
649,817
kWh
$2,402
438
kW-months/year
$15,910
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Electricity Fees Electricity Usage Electricity Demand Electricity Fees