IAC Assessment: BS0107
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BS0107
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Boise State University
Assessment Year 2017
Principal Product Plywood
NAICS 321113 - Sawmills
SIC 2421 - Sawmills And Planing Mills, General
Sales $10,000,000-$50,000,000
# of Employees 200
Plant Area (Sq.Ft.) 117,500
Annual Production 280,000 Units
Production Hrs. Annual 8,128
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,826,665 34,844,804 kWh $0.05
Electricity Demand $390,061 59,514 kW-months/year $6.55
Natural Gas $796,677 184,154 MMBtu $4.33
TOTAL ENERGY COSTS $3,013,404
RECOMMENDED SAVINGS* $96,277 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$4,338
Cost:
$5,117
- - - - $4,338 1,002 -
-
kWh
-
-
kW-months/year
$4,338
1,002
MMBtu
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,846
Cost:
$2,224
$2,433 46,428 $413 63 - - $2,433
46,428
kWh
$413
63
kW-months/year
-
-
MMBtu
03: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$23,395
Cost:
$2,640
$19,975 381,200 $3,420 522 - - $19,975
381,200
kWh
$3,420
522
kW-months/year
-
-
MMBtu
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$54,676
Cost:
$1,500
$46,683 890,892 $7,994 1,220 - - $46,683
890,892
kWh
$7,994
1,220
kW-months/year
-
-
MMBtu
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,021
Cost:
$32,160
$9,410 179,580 $1,611 246 - - $9,410
179,580
kWh
$1,611
246
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$96,277
Cost:
$43,641
$78,500 1,498,100 $13,438 2,052 $4,338 1,002 $78,500
1,498,100
kWh
$13,438
2,052
kW-months/year
$4,338
1,002
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas