Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Boise State University |
---|---|
Assessment Year | 2019 |
Principal Product | Ornimental Brass Hardware |
NAICS | 332323 - Ornamental and Architectural Metal Work Manufacturing |
SIC | 3446 - Architectural Metal Work |
Sales | $10,000,000-$50,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 61,000 |
Annual Production | 3,100 Tons |
Production Hrs. Annual | 2,480 |
Location (State) | ID |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $90,439 | 1,579,598 | kWh | $0.06 |
Electricity Demand | $59,326 | 10,931 | kW-months/year | $5.43 |
Electricity Fees | $1,201 | - | $ | - |
Natural Gas | $17,494 | 3,134 | MMBtu | $5.58 |
TOTAL ENERGY COSTS | $168,460 | |||
RECOMMENDED SAVINGS* | $8,488 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $109 Cost: $125 |
$79 | 1,380 | $30 | 6 | - | - |
$79 1,380 kWh |
$30 6 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $178 Cost: $218 |
$122 | 2,124 | $56 | 10 | - | - |
$122 2,124 kWh |
$56 10 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $904 Cost: $880 |
$(-5) | (-84) | - | - | $909 | 165 |
$(-5) (-84) kWh |
- - kW-months/year |
$909 165 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $1,514 Cost: $1,010 |
$1,021 | 17,830 | $493 | 91 | - | - |
$1,021 17,830 kWh |
$493 91 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,663 Cost: $512 |
$1,448 | 25,296 | $2,215 | 408 | - | - |
$1,448 25,296 kWh |
$2,215 408 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $354 Cost: $796 |
$354 | 6,191 | - | - | - | - |
$354 6,191 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,509 Cost: $810 |
$1,509 | 26,350 | - | - | - | - |
$1,509 26,350 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $257 Cost: $56 |
$172 | 3,008 | $85 | 16 | - | - |
$172 3,008 kWh |
$85 16 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,488 Cost: $4,407 |
$4,700 | 82,096 | $2,879 | 530 | $909 | 165 | $4,700 82,096 kWh |
$2,879 530 kW-months/year |
$909 165 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |