IAC Assessment: BS0127
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: BS0127
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Boise State University
Assessment Year 2019
Principal Product Iron Castings
NAICS 331511 - Iron Foundries
SIC 3321 - Gray And Ductile Iron Foundries
Sales $1,000,000-$5,000,000
# of Employees 200
Plant Area (Sq.Ft.) 1,194,881
Annual Production 30,000 Tons
Production Hrs. Annual 5,800
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $592,761 29,803,200 kWh $0.02
Electricity Demand $465,743 91,723 kW-months/year $5.08
Electricity Fees $1,014 - $ -
Natural Gas $117,232 36,635 MMBtu $3.20
TOTAL ENERGY COSTS $1,176,750
RECOMMENDED SAVINGS* $19,496 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$444
Cost:
$240
$444 22,222 - - $444
22,222
kWh
-
-
kW-months/year
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,465
Cost:
$10,665
$3,365 168,244 $1,100 217 $3,365
168,244
kWh
$1,100
217
kW-months/year
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,969
Cost:
$1,830
$1,296 64,794 $673 133 $1,296
64,794
kWh
$673
133
kW-months/year
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$5,701
Cost:
$2,200
$3,264 163,200 $2,437 480 $3,264
163,200
kWh
$2,437
480
kW-months/year
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,941
Cost:
$9,000
$1,345 67,271 $3,596 708 $1,345
67,271
kWh
$3,596
708
kW-months/year
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,976
Cost:
$50
$1,307 65,331 $669 132 $1,307
65,331
kWh
$669
132
kW-months/year
TOTAL RECOMMENDED Savings:
$19,496
Cost:
$23,985
$11,021 551,062 $8,475 1,669 $11,021
551,062
kWh
$8,475
1,669
kW-months/year
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand