Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1985 |
Principal Product | FREQUENCY CRYSTALS |
NAICS | n/a |
SIC | 3679 - Electronic Components, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 115 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 3,600,000 Pieces |
Production Hrs. Annual | 4,186 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $37,164 | 550,117 | kWh | $0.07 |
Natural Gas | $8,347 | 1,964 | MMBtu | $4.25 |
TOTAL ENERGY COSTS | $45,511 | |||
RECOMMENDED SAVINGS* | $31,309 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $30,446 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,938 Cost: $798 |
$1,938 | 28,722 | - | - |
$1,938 28,722 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $511 Cost: $300 |
- | - | $511 | 103 |
- - kWh |
$511 103 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7312 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE |
Savings: $17,952 Cost: $100 |
$17,952 | 265,826 | - | - |
$17,952 265,826 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $54 Cost: $92 |
- | - | $54 | 11 |
- - kWh |
$54 11 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $304 Cost: $51 |
$71 | 1,172 | $233 | 47 |
$71 1,172 kWh |
$233 47 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $550 Cost: $210 |
- | - | $550 | 111 |
- - kWh |
$550 111 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $8,891 Cost: $2,400 |
$6,485 | 96,131 | $2,406 | 487 |
$6,485 96,131 kWh |
$2,406 487 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.5122 REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS |
Savings: $246 Cost: $50 |
$246 | 3,517 | - | - |
$246 3,517 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $863 Cost: $500 |
$863 | 12,896 | - | - |
$863 12,896 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $31,309 Cost: $4,501 |
$27,555 | 408,264 | $3,754 | 759 | $27,555 408,264 kWh |
$3,754 759 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $30,446 Cost: $4,001 |
$26,692 | 395,368 | $3,754 | 759 | $26,692 395,368 kWh |
$3,754 759 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |