IAC logo
IAC Assessment: CO0102
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0102
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 1987
Principal Product MEDICAL EQUIPMENT
NAICS n/a
SIC 3841 - Surgical And Medical Instruments
Sales $1,000,000-$5,000,000
# of Employees 50
Plant Area (Sq.Ft.) 0
Annual Production 4,400 Pieces
Production Hrs. Annual 2,125
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $39,657 757,034 kWh $0.05
Natural Gas $28,490 6,987 MMBtu $4.08
TOTAL ENERGY COSTS $68,147
RECOMMENDED SAVINGS* $14,958 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $14,958
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$825
Cost:
$200
$825 15,826 - - $825
15,826
kWh
-
-
MMBtu
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$72
Cost:
$50
$72 1,465 - - $72
1,465
kWh
-
-
MMBtu
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$8,334
Cost:
$3,600
- - $8,334 2,042 -
-
kWh
$8,334
2,042
MMBtu
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$3,060
Cost:
$3,010
$3,060 - - - $3,060
-
kWh
-
-
MMBtu
05: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE Savings:
$139
Cost:
$450
- - $139 34 -
-
kWh
$139
34
MMBtu
06: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$1,703
Cost:
$250
$1,703 - - - $1,703
-
kWh
-
-
MMBtu
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$825
Cost:
$558
$825 15,826 - - $825
15,826
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$14,958
Cost:
$8,118
$6,485 33,117 $8,473 2,076 $6,485
33,117
kWh
$8,473
2,076
MMBtu
TOTAL IMPLEMENTED Savings:
$14,958
Cost:
$8,118
$6,485 33,117 $8,473 2,076 $6,485
33,117
kWh
$8,473
2,076
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas