IAC logo
IAC Assessment: CO0402
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0402
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 1997
Principal Product wood display cabinets & fixtures
NAICS n/a
SIC 2541 - Wood Partitions And Fixtures
Sales $5,000,000-$10,000,000
# of Employees 70
Plant Area (Sq.Ft.) 80,000
Annual Production 2,000 Pieces
Production Hrs. Annual 5,720
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $19,184 1,103,458 kWh $0.02
Electricity Demand $46,747 3,494 kW-months/year $13.38
Electricity Fees $216 - $ -
Natural Gas $12,176 3,375 MMBtu $3.61
TOTAL ENERGY COSTS $80,123
RECOMMENDED SAVINGS* $49,825 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (haz) Personnel Changes Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Solid Waste (haz) Personnel Changes Ancillary Material Cost Primary Product
$ kWh $ kW-months/year $ lb $ $ $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$635
Cost:
$995
$147 8,499 $488 36 - - - - - - - - $147
8,499
kWh
$488
36
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$1,200
Cost:
$2,920
$1,200 69,461 - - - - - - - - - - $1,200
69,461
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
03: 3.8125 REMOVE ROLLERS FROM THE MACHINES AND CLEAN IN A CLOSED SOLVENT CLEANER Savings:
$1,180
Cost:
$1,000
- - - - - - $910 - $270 - - - -
-
kWh
-
-
kW-months/year
-
-
lb
$910
-
$
$270
-
$
-
-
$
04: 3.8132 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES Savings:
$930
Cost:
-
- - - - $760 70 - - $170 - - - -
-
kWh
-
-
kW-months/year
$760
70
lb
-
-
$
$170
-
$
-
-
$
05: 3.8132 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES Savings:
$970
Cost:
-
- - - - - - - - $970 - - - -
-
kWh
-
-
kW-months/year
-
-
lb
-
-
$
$970
-
$
-
-
$
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$360
Cost:
-
- - - - $360 80 - - - - - - -
-
kWh
-
-
kW-months/year
$360
80
lb
-
-
$
-
-
$
-
-
$
07: 4.4510 ADD ADDITIONAL PRODUCTION SHIFT Savings:
$35,580
Cost:
$730
$(-190) (-10,844) - - - - $(-2,990) - - - $38,760 - $(-190)
(-10,844)
kWh
-
-
kW-months/year
-
-
lb
$(-2,990)
-
$
-
-
$
$38,760
-
$
08: 4.5140 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS Savings:
$8,970
Cost:
$20,000
- - - - - - $8,970 - - - - - -
-
kWh
-
-
kW-months/year
-
-
lb
$8,970
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$49,825
Cost:
$25,645
$1,157 67,116 $488 36 $1,120 150 $6,890 - $1,410 - $38,760 - $1,157
67,116
kWh
$488
36
kW-months/year
$1,120
150
lb
$6,890
-
$
$1,410
-
$
$38,760
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
lb
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ $ $ $ $ $
Electricity Usage Electricity Demand Solid Waste (haz) Personnel Changes Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Solid Waste (haz) Personnel Changes Ancillary Material Cost Primary Product