Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1997 |
Principal Product | beer |
NAICS | n/a |
SIC | 2082 - Malt Beverages |
Sales | $5,000,000-$10,000,000 |
# of Employees | 175 |
Plant Area (Sq.Ft.) | 30,000 |
Annual Production | 160,260 Thousand Gallons |
Production Hrs. Annual | 2,210 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $19,101 | 1,001,465 | kWh | $0.02 |
Electricity Demand | $27,852 | 1,902 | kW-months/year | $14.64 |
Electricity Fees | $312 | - | $ | - |
Natural Gas | $10,321 | 2,607 | MMBtu | $3.96 |
Other Energy | $38,508 | 4,866 | MMBtu | $7.91 |
TOTAL ENERGY COSTS | $122,224 | |||
RECOMMENDED SAVINGS* | $12,822 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Energy | Personnel Changes | Electricity Usage | Electricity Demand | Other Energy | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,072 Cost: $6,685 |
$2,952 | 148,007 | $3,120 | 226 | - | - | - | - |
$2,952 148,007 kWh |
$3,120 226 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2623 MINIMIZE CONDENSER COOLING WATER TEMPERATURE |
Savings: $1,790 Cost: $2,000 |
$280 | 14,654 | $300 | 20 | $1,210 | 130 | - | - |
$280 14,654 kWh |
$300 20 kW-months/year |
$1,210 130 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $1,180 Cost: - |
$210 | 11,137 | $970 | 67 | - | - | - | - |
$210 11,137 kWh |
$970 67 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $380 Cost: $300 |
- | - | - | - | $380 | 41 | - | - |
- - kWh |
- - kW-months/year |
$380 41 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $280 Cost: $810 |
- | - | - | - | $280 | 30 | - | - |
- - kWh |
- - kW-months/year |
$280 30 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.452 ELIMINATE SHIFT |
Savings: $3,120 Cost: - |
- | - | - | - | - | - | $3,120 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$3,120 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $12,822 Cost: $9,795 |
$3,442 | 173,798 | $4,390 | 313 | $1,870 | 201 | $3,120 | - | $3,442 173,798 kWh |
$4,390 313 kW-months/year |
$1,870 201 MMBtu |
$3,120 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Energy | Personnel Changes | Electricity Usage | Electricity Demand | Other Energy | Personnel Changes |