Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 1998 |
Principal Product | finished metal components |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $1,000,000-$5,000,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 11,250 |
Annual Production | 8,850 Pieces |
Production Hrs. Annual | 4,290 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $19,336 | 889,801 | kWh | $0.02 |
Electricity Demand | $41,319 | 2,931 | kW-months/year | $14.10 |
Electricity Fees | $590 | - | $ | - |
Natural Gas | $10,953 | 2,346 | MMBtu | $4.67 |
TOTAL ENERGY COSTS | $95,192 | |||
RECOMMENDED SAVINGS* | $15,360 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,700 |
#|Description |
Savings Cost |
Status | Electricity Demand | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product | Electricity Demand | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kW-months/year | $ | gal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $840 Cost: $1,000 |
$840 | 60 | - | - | - | - | - | - | - | - |
$840 60 kW-months/year |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.2161 CLOSELY MONITOR CHEMICAL ADDITIONS TO INCREASE BATH LIFE |
Savings: $4,860 Cost: - |
- | - | $2,050 | 300 | $60 | - | $2,750 | - | - | - |
- - kW-months/year |
$2,050 300 gal |
$60 - $ |
$2,750 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.1242 ALLOW DRAINAGE BEFORE WITHDRAWING OBJECT |
Savings: $2,930 Cost: $800 |
- | - | - | - | $320 | - | $2,610 | - | - | - |
- - kW-months/year |
- - gal |
$320 - $ |
$2,610 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $6,000 Cost: $10,160 |
- | - | - | - | - | - | - | - | $6,000 | - |
- - kW-months/year |
- - gal |
- - $ |
- - $ |
$6,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.514 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS |
Savings: $730 Cost: $280 |
- | - | - | - | - | - | - | - | $730 | - |
- - kW-months/year |
- - gal |
- - $ |
- - $ |
$730 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $15,360 Cost: $12,240 |
$840 | 60 | $2,050 | 300 | $380 | - | $5,360 | - | $6,730 | - | $840 60 kW-months/year |
$2,050 300 gal |
$380 - $ |
$5,360 - $ |
$6,730 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,700 Cost: $11,160 |
$840 | 60 | $2,050 | 300 | $60 | - | $2,750 | - | $6,000 | - | $840 60 kW-months/year |
$2,050 300 gal |
$60 - $ |
$2,750 - $ |
$6,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kW-months/year | $ | gal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Demand | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product | Electricity Demand | Other Liquid (haz) | Personnel Changes | Ancillary Material Cost | Primary Product |