IAC Assessment: CO0523
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0523
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 2003
Principal Product Concrete pipe & prestressed concrete products
NAICS 327332 - Concrete Pipe Manufacturing
SIC 3272 - Concrete Products, Nec
Sales $100,000,000-$500,000,000
# of Employees 135
Plant Area (Sq.Ft.) 46,800
Annual Production 230,000 Tons
Production Hrs. Annual 5,408
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $32,308 1,959,601 kWh $0.02
Electricity Demand $99,441 7,893 kW-months/year $12.60
Electricity Fees $1,665 - $ -
Natural Gas $175,144 32,217 MMBtu $5.44
TOTAL ENERGY COSTS $312,474
RECOMMENDED SAVINGS* $46,726 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,120
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$19,740
Cost:
$12,000
$5,350 232,900 $14,390 1,086 - - - - $5,350
232,900
kWh
$14,390
1,086
kW-months/year
-
-
MMBtu
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$10,270
Cost:
$19,440
$4,440 193,300 $5,680 429 - - $150 - $4,440
193,300
kWh
$5,680
429
kW-months/year
-
-
MMBtu
$150
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$6,990
Cost:
$230
$3,380 147,300 $4,330 327 - - $(-720) - $3,380
147,300
kWh
$4,330
327
kW-months/year
-
-
MMBtu
$(-720)
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,122
Cost:
$12,500
$2,228 97,070 $2,090 158 - - $(-196) - $2,228
97,070
kWh
$2,090
158
kW-months/year
-
-
MMBtu
$(-196)
-
$
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$4,120
Cost:
$11,840
$(-160) (-6,800) $(-120) (-9) $4,400 998 - - $(-160)
(-6,800)
kWh
$(-120)
(-9)
kW-months/year
$4,400
998
MMBtu
-
-
$
06: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$1,130
Cost:
$210
- - - - $1,130 257 - - -
-
kWh
-
-
kW-months/year
$1,130
257
MMBtu
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$144
Cost:
$266
$40 1,710 $92 7 - - $12 - $40
1,710
kWh
$92
7
kW-months/year
-
-
MMBtu
$12
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$210
Cost:
$490
$110 4,806 $144 11 - - $(-44) - $110
4,806
kWh
$144
11
kW-months/year
-
-
MMBtu
$(-44)
-
$
TOTAL RECOMMENDED Savings:
$46,726
Cost:
$56,976
$15,388 670,286 $26,606 2,009 $5,530 1,255 $(-798) - $15,388
670,286
kWh
$26,606
2,009
kW-months/year
$5,530
1,255
MMBtu
$(-798)
-
$
TOTAL IMPLEMENTED Savings:
$8,120
Cost:
$440
$3,380 147,300 $4,330 327 $1,130 257 $(-720) - $3,380
147,300
kWh
$4,330
327
kW-months/year
$1,130
257
MMBtu
$(-720)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost