Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2003 |
Principal Product | Sub-bituminous coal |
NAICS | 212111 - Bituminous Coal and Lignite Surface Mining |
SIC | 1221 - Bituminous Coal And Lignitesurface |
Sales | $100,000,000-$500,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 20,000,000 Tons |
Production Hrs. Annual | 8,760 |
Location (State) | WY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $539,951 | 31,461,500 | kWh | $0.02 |
Electricity Demand | $500,576 | 69,087 | kW-months/year | $7.25 |
Electricity Fees | $5,700 | - | $ | - |
Natural Gas | $79,358 | 22,014 | MMBtu | $3.60 |
TOTAL ENERGY COSTS | $1,125,585 | |||
RECOMMENDED SAVINGS* | $28,591 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,121 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4325 UPGRADE CONVEYORS |
Savings: $19,310 Cost: $46,220 |
$10,550 | 560,200 | $5,830 | 842 | $1,440 | - | $1,490 | - |
$10,550 560,200 kWh |
$5,830 842 kW-months/year |
$1,440 - $ |
$1,490 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,122 Cost: $26,560 |
$2,799 | 148,656 | $2,372 | 342 | $342 | - | $(-391) | - |
$2,799 148,656 kWh |
$2,372 342 kW-months/year |
$342 - $ |
$(-391) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,530 Cost: $6,580 |
$1,380 | 73,400 | $1,150 | 166 | - | - | - | - |
$1,380 73,400 kWh |
$1,150 166 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4222 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN |
Savings: $1,160 Cost: $4,000 |
$770 | 40,800 | $390 | 56 | - | - | - | - |
$770 40,800 kWh |
$390 56 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $330 Cost: $110 |
$220 | 11,800 | $110 | 16 | - | - | - | - |
$220 11,800 kWh |
$110 16 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $139 Cost: $139 |
$82 | 4,351 | $69 | 10 | - | - | $(-12) | - |
$82 4,351 kWh |
$69 10 kW-months/year |
- - $ |
$(-12) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,591 Cost: $83,609 |
$15,801 | 839,207 | $9,921 | 1,432 | $1,782 | - | $1,087 | - | $15,801 839,207 kWh |
$9,921 1,432 kW-months/year |
$1,782 - $ |
$1,087 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,121 Cost: $33,389 |
$4,481 | 238,207 | $3,701 | 534 | $342 | - | $(-403) | - | $4,481 238,207 kWh |
$3,701 534 kW-months/year |
$342 - $ |
$(-403) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost |