IAC Center | Colorado State University |
---|---|
Assessment Year | 2005 |
Principal Product | Wood doors & architectural millwork |
NAICS | 321911 - Wood Window and Door Manufacturing |
SIC | 2431 - Millwork |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 68,000 |
Annual Production | 26,000 Pieces |
Production Hrs. Annual | 2,210 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $42,910 | 898,200 | kWh | $0.05 |
Electricity Demand | $52,946 | 3,809 | kW-months/year | $13.90 |
Natural Gas | $14,520 | 1,755 | MMBtu | $8.27 |
TOTAL ENERGY COSTS | $155,900 | |||
RECOMMENDED SAVINGS* | $423,400 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $345,470 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.132 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST |
Savings: $329,210 Cost: $400,000 |
- | - | - | - | - | - | - | - | $29,210 | 2,604 | - | - | $300,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$29,210 2,604 lb |
- - $ |
$300,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $62,190 Cost: $230,000 |
$20,740 | 306,900 | $8,650 | 600 | $13,530 | 1,755 | - | - | $19,270 | 646,200 | - | - | - | - | - | - |
$20,740 306,900 kWh |
$8,650 600 kW-months/year |
$13,530 1,755 MMBtu |
- - gal |
$19,270 646,200 lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.8125 REMOVE ROLLERS FROM THE MACHINES AND CLEAN IN A CLOSED SOLVENT CLEANER |
Savings: $4,750 Cost: $1,150 |
- | - | - | - | - | - | $1,050 | 371 | - | - | $610 | - | - | - | $3,090 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,050 371 gal |
- - lb |
$610 - $ |
- - $ |
$3,090 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,710 Cost: $200 |
$780 | 15,400 | $930 | 65 | - | - | - | - | - | - | - | - | - | - | - | - |
$780 15,400 kWh |
$930 65 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,370 Cost: $600 |
$780 | 15,200 | $590 | 41 | - | - | - | - | - | - | - | - | - | - | - | - |
$780 15,200 kWh |
$590 41 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $670 Cost: $1,290 |
$280 | 5,400 | $390 | 27 | - | - | - | - | - | - | - | - | - | - | - | - |
$280 5,400 kWh |
$390 27 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7145 INSTALL SKYLIGHTS |
Savings: $12,750 Cost: $90,400 |
$5,990 | 117,400 | $6,340 | 440 | - | - | - | - | - | - | $190 | - | - | - | $230 | - |
$5,990 117,400 kWh |
$6,340 440 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$190 - $ |
- - $ |
$230 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,270 Cost: $4,000 |
$3,220 | 63,100 | $3,820 | 265 | - | - | - | - | - | - | $120 | - | - | - | $110 | - |
$3,220 63,100 kWh |
$3,820 265 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$120 - $ |
- - $ |
$110 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.9111 USE SOLAR HEAT TO HEAT MAKE-UP AIR |
Savings: $2,170 Cost: $23,570 |
$(-200) | (-4,000) | $(-140) | (-10) | $2,510 | 325 | - | - | - | - | - | - | - | - | - | - |
$(-200) (-4,000) kWh |
$(-140) (-10) kW-months/year |
$2,510 325 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $760 Cost: $1,050 |
$320 | 6,300 | $420 | 22 | - | - | - | - | - | - | $10 | - | - | - | $10 | - |
$320 6,300 kWh |
$420 22 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$10 - $ |
- - $ |
$10 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $400 Cost: $440 |
$90 | 1,800 | $30 | 2 | - | - | - | - | - | - | $60 | - | - | - | $220 | - |
$90 1,800 kWh |
$30 2 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$60 - $ |
- - $ |
$220 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $150 Cost: $390 |
$150 | 3,000 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$150 3,000 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $423,400 Cost: $753,090 |
$32,150 | 530,500 | $21,030 | 1,452 | $16,040 | 2,080 | $1,050 | 371 | $48,480 | 648,804 | $990 | - | $300,000 | - | $3,660 | - | $32,150 530,500 kWh |
$21,030 1,452 kW-months/year |
$16,040 2,080 MMBtu |
$1,050 371 gal |
$48,480 648,804 lb |
$990 - $ |
$300,000 - $ |
$3,660 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $345,470 Cost: $407,440 |
$5,190 | 101,800 | $5,790 | 395 | - | - | $1,050 | 371 | $29,210 | 2,604 | $800 | - | $300,000 | - | $3,430 | - | $5,190 101,800 kWh |
$5,790 395 kW-months/year |
- - MMBtu |
$1,050 371 gal |
$29,210 2,604 lb |
$800 - $ |
$300,000 - $ |
$3,430 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Primary Raw Material | Ancillary Material Cost |