Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2010 |
Principal Product | Asphalt plants, tanks and heaters |
NAICS | 333120 - Construction Machinery Manufacturing |
SIC | 3531 - Construction Machinery |
Sales | $10,000,000-$50,000,000 |
# of Employees | 84 |
Plant Area (Sq.Ft.) | 196,000 |
Annual Production | 12 Pieces |
Production Hrs. Annual | 2,817 |
Location (State) | NM |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $71,454 | 804,384 | kWh | $0.09 |
Electricity Demand | $18,712 | 4,051 | kW-months/year | $4.62 |
Electricity Fees | $3,766 | - | $ | - |
Natural Gas | $85,175 | 10,869 | MMBtu | $7.84 |
TOTAL ENERGY COSTS | $179,107 | |||
RECOMMENDED SAVINGS* | $21,780 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,480 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,850 Cost: $12,690 |
$9,480 | 88,900 | $2,150 | 389 | $80 | - | - | - | $140 | - |
$9,480 88,900 kWh |
$2,150 389 kW-months/year |
$80 - $ |
- - $ |
$140 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $4,300 Cost: $27,000 |
$1,820 | 15,600 | $340 | 62 | - | - | $2,140 | - | - | - |
$1,820 15,600 kWh |
$340 62 kW-months/year |
- - $ |
$2,140 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,530 Cost: $4,090 |
$2,040 | 17,500 | $490 | 90 | $30 | - | - | - | $(-30) | - |
$2,040 17,500 kWh |
$490 90 kW-months/year |
$30 - $ |
- - $ |
$(-30) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,360 Cost: $6,090 |
$1,850 | 17,400 | $490 | 89 | $20 | - | - | - | - | - |
$1,850 17,400 kWh |
$490 89 kW-months/year |
$20 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $740 Cost: $1,320 |
$320 | 3,000 | $80 | 15 | $290 | - | - | - | $50 | - |
$320 3,000 kWh |
$80 15 kW-months/year |
$290 - $ |
- - $ |
$50 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $21,780 Cost: $51,190 |
$15,510 | 142,400 | $3,550 | 645 | $420 | - | $2,140 | - | $160 | - | $15,510 142,400 kWh |
$3,550 645 kW-months/year |
$420 - $ |
$2,140 - $ |
$160 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,480 Cost: $24,190 |
$13,690 | 126,800 | $3,210 | 583 | $420 | - | - | - | $160 | - | $13,690 126,800 kWh |
$3,210 583 kW-months/year |
$420 - $ |
- - $ |
$160 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost |