Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2012 |
Principal Product | Erosion and sediment control products |
NAICS | 321999 - All Other Miscellaneous Wood Product Manufacturing |
SIC | 2429 - Special Product Sawmills, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 81,000 |
Annual Production | 6,240 Tons |
Production Hrs. Annual | 5,512 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $347,147 | 3,407,420 | kWh | $0.10 |
Electricity Demand | $94,999 | 14,151 | kW-months/year | $6.71 |
Electricity Fees | $5,349 | - | $ | - |
Natural Gas | $9,724 | 1,601 | MMBtu | $6.07 |
TOTAL ENERGY COSTS | $457,219 | |||
RECOMMENDED SAVINGS* | $88,560 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,710 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $25,240 Cost: $155,860 |
$18,180 | 221,800 | $7,060 | 656 | - | - |
$18,180 221,800 kWh |
$7,060 656 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,710 Cost: $1,000 |
$4,590 | 60,100 | $1,120 | 104 | - | - |
$4,590 60,100 kWh |
$1,120 104 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $3,090 Cost: $430 |
$2,490 | 32,600 | $600 | 56 | - | - |
$2,490 32,600 kWh |
$600 56 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $30,160 Cost: $56,610 |
- | - | $30,160 | 2,802 | - | - |
- - kWh |
$30,160 2,802 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $14,630 Cost: $32,970 |
$11,240 | 140,600 | $3,290 | 306 | $210 | - |
$11,240 140,600 kWh |
$3,290 306 kW-months/year |
$210 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,730 Cost: $13,270 |
$7,110 | 90,500 | $2,350 | 218 | $160 | - |
$7,110 90,500 kWh |
$2,350 218 kW-months/year |
$160 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $88,560 Cost: $260,140 |
$43,610 | 545,600 | $44,580 | 4,142 | $370 | - | $43,610 545,600 kWh |
$44,580 4,142 kW-months/year |
$370 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,710 Cost: $1,000 |
$4,590 | 60,100 | $1,120 | 104 | - | - | $4,590 60,100 kWh |
$1,120 104 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes |