Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2013 |
Principal Product | Computer display kiosks |
NAICS | 334118 - Computer Terminal and Other Computer Peripheral Equipment Manufacturing |
SIC | 3577 - Computer Peripheral Equipment, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 104,250 |
Annual Production | 9,000 Pieces |
Production Hrs. Annual | 6,864 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $65,762 | 1,682,429 | kWh | $0.04 |
Electricity Demand | $92,046 | 4,344 | kW-months/year | $21.19 |
Electricity Fees | $1,827 | - | $ | - |
Natural Gas | $37,322 | 5,987 | MMBtu | $6.23 |
TOTAL ENERGY COSTS | $196,957 | |||
RECOMMENDED SAVINGS* | $17,070 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,500 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,670 Cost: $310 |
$1,410 | 33,800 | $1,260 | 59 | - | - | - | - | - | - |
$1,410 33,800 kWh |
$1,260 59 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM |
Savings: $4,510 Cost: $13,600 |
$1,440 | 34,500 | $3,070 | 144 | - | - | - | - | - | - |
$1,440 34,500 kWh |
$3,070 144 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $3,740 Cost: - |
$1,070 | 25,700 | $2,670 | 125 | - | - | - | - | - | - |
$1,070 25,700 kWh |
$2,670 125 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $4,320 Cost: $500 |
- | - | - | - | - | - | $4,320 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$4,320 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,830 Cost: $250 |
$550 | 13,200 | $1,180 | 56 | $120 | - | - | - | $(-20) | - |
$550 13,200 kWh |
$1,180 56 kW-months/year |
$120 - $ |
- - $ |
$(-20) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,070 Cost: $14,660 |
$4,470 | 107,200 | $8,180 | 384 | $120 | - | $4,320 | - | $(-20) | - | $4,470 107,200 kWh |
$8,180 384 kW-months/year |
$120 - $ |
$4,320 - $ |
$(-20) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,500 Cost: $560 |
$1,960 | 47,000 | $2,440 | 115 | $120 | - | - | - | $(-20) | - | $1,960 47,000 kWh |
$2,440 115 kW-months/year |
$120 - $ |
- - $ |
$(-20) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost |