Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2013 |
Principal Product | Brewed beverages |
NAICS | 312120 - Breweries |
SIC | 2082 - Malt Beverages |
Sales | $50,000,000-$100,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 34,000 |
Annual Production | 130,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $48,039 | 1,435,776 | kWh | $0.03 |
Electricity Demand | $54,806 | 3,599 | kW-months/year | $15.23 |
Electricity Fees | $948 | - | $ | - |
Natural Gas | $65,579 | 13,577 | MMBtu | $4.83 |
TOTAL ENERGY COSTS | $169,372 | |||
RECOMMENDED SAVINGS* | $12,510 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,630 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL |
Savings: $3,450 Cost: $14,200 |
$1,720 | 48,600 | $1,730 | 110 | - | - | - | - | - | - | - | - |
$1,720 48,600 kWh |
$1,730 110 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $2,660 Cost: $1,620 |
- | - | - | - | $2,660 | 550 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,660 550 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $520 Cost: - |
$210 | 6,000 | $310 | 20 | - | - | - | - | - | - | - | - |
$210 6,000 kWh |
$310 20 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $430 Cost: $2,450 |
$260 | 7,500 | $170 | 11 | - | - | - | - | - | - | - | - |
$260 7,500 kWh |
$170 11 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $4,810 Cost: - |
- | - | - | - | - | - | - | - | $4,810 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$4,810 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $640 Cost: $3,450 |
$580 | 16,300 | - | - | - | - | $40 | - | - | - | $20 | - |
$580 16,300 kWh |
- - kW-months/year |
- - MMBtu |
$40 - $ |
- - $ |
$20 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $12,510 Cost: $21,720 |
$2,770 | 78,400 | $2,210 | 141 | $2,660 | 550 | $40 | - | $4,810 | - | $20 | - | $2,770 78,400 kWh |
$2,210 141 kW-months/year |
$2,660 550 MMBtu |
$40 - $ |
$4,810 - $ |
$20 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,630 Cost: $5,070 |
$790 | 22,300 | $310 | 20 | $2,660 | 550 | $40 | - | $4,810 | - | $20 | - | $790 22,300 kWh |
$310 20 kW-months/year |
$2,660 550 MMBtu |
$40 - $ |
$4,810 - $ |
$20 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost |