Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Colorado State University |
---|---|
Assessment Year | 2014 |
Principal Product | Oil & Gas Well Optimization Equipment |
NAICS | 333911 - Pump and Pumping Equipment Manufacturing |
SIC | 3561 - Pumps And Pumping Equipment |
Sales | $100,000,000-$500,000,000 |
# of Employees | 390 |
Plant Area (Sq.Ft.) | 45,700 |
Annual Production | 420,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | CO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $69,335 | 1,205,760 | kWh | $0.06 |
Electricity Demand | $43,151 | 2,400 | kW-months/year | $17.98 |
Electricity Fees | $756 | - | $ | - |
Natural Gas | $4,454 | 576 | MMBtu | $7.73 |
TOTAL ENERGY COSTS | $117,696 | |||
RECOMMENDED SAVINGS* | $13,460 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,320 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,210 Cost: $2,210 |
$3,770 | 62,100 | $1,440 | 85 | - | - | - | - | - | - |
$3,770 62,100 kWh |
$1,440 85 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,220 Cost: $6,060 |
$2,090 | 34,400 | $980 | 58 | $60 | - | - | - | $90 | - |
$2,090 34,400 kWh |
$980 58 kW-months/year |
$60 - $ |
- - $ |
$90 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $3,110 Cost: $1,500 |
- | - | - | - | - | - | $3,110 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$3,110 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,920 Cost: $2,480 |
$1,800 | 29,700 | - | - | $30 | - | - | - | $90 | - |
$1,800 29,700 kWh |
- - kW-months/year |
$30 - $ |
- - $ |
$90 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,460 Cost: $12,250 |
$7,660 | 126,200 | $2,420 | 143 | $90 | - | $3,110 | - | $180 | - | $7,660 126,200 kWh |
$2,420 143 kW-months/year |
$90 - $ |
$3,110 - $ |
$180 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,320 Cost: $3,710 |
$3,770 | 62,100 | $1,440 | 85 | - | - | $3,110 | - | - | - | $3,770 62,100 kWh |
$1,440 85 kW-months/year |
- - $ |
$3,110 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Ancillary Material Cost |