IAC Assessment: CO0697
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0697
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 2014
Principal Product Precision optical components
NAICS 333314 - Optical Instrument and Lens Manufacturing
SIC 3827 - Optical Instruments And Lenses
Sales $5,000,000-$10,000,000
# of Employees 33
Plant Area (Sq.Ft.) 40,700
Annual Production 22,000 Pieces
Production Hrs. Annual 2,210
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $62,886 1,342,080 kWh $0.05
Electricity Demand $58,530 2,641 kW-months/year $22.16
Electricity Fees $637 - $ -
Natural Gas $13,494 1,792 MMBtu $7.53
TOTAL ENERGY COSTS $135,547
RECOMMENDED SAVINGS* $55,170 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Primary Product
$ kWh $ kW-months/year $ $ $ $ $ $ $ $
01: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL Savings:
$23,320
Cost:
$29,550
$(-1,500) (-31,300) $(-950) (-43) - - - - - - $25,770 - $(-1,500)
(-31,300)
kWh
$(-950)
(-43)
kW-months/year
-
-
$
-
-
$
-
-
$
$25,770
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,760
Cost:
$1,550
$2,920 60,900 $1,840 83 - - - - - - - - $2,920
60,900
kWh
$1,840
83
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
03: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$13,090
Cost:
$87,610
$6,400 133,700 - - - - $6,690 - - - - - $6,400
133,700
kWh
-
-
kW-months/year
-
-
$
$6,690
-
$
-
-
$
-
-
$
04: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM Savings:
$8,560
Cost:
$38,890
$3,760 78,400 $4,800 232 - - - - - - - - $3,760
78,400
kWh
$4,800
232
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
05: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$4,000
Cost:
$500
- - - - - - $4,000 - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$4,000
-
$
-
-
$
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,440
Cost:
$5,180
$360 7,500 $900 41 $20 - - - $160 - - - $360
7,500
kWh
$900
41
kW-months/year
$20
-
$
-
-
$
$160
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$55,170
Cost:
$163,280
$11,940 249,200 $6,590 313 $20 - $10,690 - $160 - $25,770 - $11,940
249,200
kWh
$6,590
313
kW-months/year
$20
-
$
$10,690
-
$
$160
-
$
$25,770
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Primary Product