IAC Assessment: CO0733
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: CO0733
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Colorado State University
Assessment Year 2016
Principal Product Knives
NAICS 332215 - Metal Kitchen Cookware, Utensil, Cutlery, and Flatware (except Precious) Manufacturing
SIC 3421 - Cutlery
Sales $10,000,000-$50,000,000
# of Employees 95
Plant Area (Sq.Ft.) 57,500
Annual Production 288,000 Units
Production Hrs. Annual 6,864
Location (State) CO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $36,500 847,563 kWh $0.04
Electricity Demand $52,181 2,387 kW-months/year $21.86
Electricity Fees $898 - $ -
Natural Gas $13,007 2,334 MMBtu $5.57
TOTAL ENERGY COSTS $102,586
RECOMMENDED SAVINGS* $17,200 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,020
Cost:
$1,730
$540 13,600 $480 21 - - - - - - $540
13,600
kWh
$480
21
kW-months/year
-
-
$
-
-
$
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$450
Cost:
$750
$220 5,500 $230 10 - - - - - - $220
5,500
kWh
$230
10
kW-months/year
-
-
$
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,360
Cost:
$5,950
$2,120 41,000 $3,110 135 $40 - - - $90 - $2,120
41,000
kWh
$3,110
135
kW-months/year
$40
-
$
-
-
$
$90
-
$
04: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$4,970
Cost:
$34,800
$1,120 28,100 $3,850 167 - - - - - - $1,120
28,100
kWh
$3,850
167
kW-months/year
-
-
$
-
-
$
-
-
$
05: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$3,200
Cost:
$500
- - - - - - $3,200 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$3,200
-
$
-
-
$
06: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM Savings:
$2,200
Cost:
$9,200
$420 10,500 $1,780 77 - - - - - - $420
10,500
kWh
$1,780
77
kW-months/year
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$17,200
Cost:
$52,930
$4,420 98,700 $9,450 410 $40 - $3,200 - $90 - $4,420
98,700
kWh
$9,450
410
kW-months/year
$40
-
$
$3,200
-
$
$90
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Administrative Changes Ancillary Material Cost