Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Case Western Reserve University |
---|---|
Assessment Year | 2020 |
Principal Product | auto parts |
NAICS | 336390 - Other Motor Vehicle Parts Manufacturing |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 65,000 |
Annual Production | 3,000 Units |
Production Hrs. Annual | 8,760 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $314,645 | 2,545,200 | kWh | $0.12 |
Natural Gas | $35,031 | 5,738 | MMBtu | $6.10 |
TOTAL ENERGY COSTS | $363,989 | |||
RECOMMENDED SAVINGS* | $73,920 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $69,932 |
#|Description |
Savings Cost |
Status | Electricity Usage | Ancillary Material Cost | Water Consumption | One-time Revenue or Avoided Cost | Electricity Usage | Ancillary Material Cost | Water Consumption | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $577 Cost: $50 |
$577 | 4,655 | - | - | - | - | - | - |
$577 4,655 kWh |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4234 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER |
Savings: $1,231 Cost: $200 |
$1,231 | 9,926 | - | - | - | - | - | - |
$1,231 9,926 kWh |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $2,856 Cost: - |
$2,856 | 22,856 | - | - | - | - | - | - |
$2,856 22,856 kWh |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,147 Cost: $3,000 |
$1,147 | 9,254 | - | - | - | - | - | - |
$1,147 9,254 kWh |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5131 RECYCLE WHITE WATER |
Savings: $1,133 Cost: - |
- | - | - | - | $1,133 | - | - | - |
- - kWh |
- - $ |
$1,133 - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4132 USE DEIONIZED WATER IN UPSTREAM RINSE TANKS |
Savings: $39,911 Cost: $4,800 |
- | - | $39,911 | - | - | - | - | - |
- - kWh |
$39,911 - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2626 AVOID FROST FORMATION ON EVAPORATORS |
Savings: $27,066 Cost: $28,000 |
$18,666 | 150,532 | - | - | - | - | $8,400 | - |
$18,666 150,532 kWh |
- - $ |
- - Tgal |
$8,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $73,920 Cost: $36,050 |
$24,477 | 197,223 | $39,911 | - | $1,133 | - | $8,400 | - | $24,477 197,223 kWh |
$39,911 - $ |
$1,133 - Tgal |
$8,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $69,932 Cost: $36,050 |
$21,621 | 174,367 | $39,911 | - | - | - | $8,400 | - | $21,621 174,367 kWh |
$39,911 - $ |
- - Tgal |
$8,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Ancillary Material Cost | Water Consumption | One-time Revenue or Avoided Cost | Electricity Usage | Ancillary Material Cost | Water Consumption | One-time Revenue or Avoided Cost |