Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2007 |
Principal Product | Ceramic Matrix Composites |
NAICS | 336412 - Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724 - Aircraft Engines And Engine Parts |
Sales | $10,000,000-$50,000,000 |
# of Employees | 51 |
Plant Area (Sq.Ft.) | 60,250 |
Annual Production | 1,000 Pounds |
Production Hrs. Annual | 8,640 |
Location (State) | DE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $580,777 | 6,604,416 | kWh | $0.09 |
Electricity Demand | $260,499 | 1,380 | kW-months/year | $188.77 |
Electricity Fees | $29,289 | - | $ | - |
Natural Gas | $260,794 | 16,380 | MMBtu | $15.92 |
TOTAL ENERGY COSTS | $1,131,359 | |||
RECOMMENDED SAVINGS* | $181,168 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $39,666 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $39,666 Cost: - |
- | - | - | - | $39,666 | - |
- - kWh |
- - MMBtu |
$39,666 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $33,000 Cost: $97,570 |
$33,000 | 357,847 | - | - | - | - |
$33,000 357,847 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,160 Cost: $800 |
$1,160 | 13,624 | - | - | - | - |
$1,160 13,624 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,933 Cost: $500 |
$2,933 | 34,434 | - | - | - | - |
$2,933 34,434 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $7,506 Cost: $33,000 |
$7,506 | 88,127 | - | - | - | - |
$7,506 88,127 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2427 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS |
Savings: $93,700 Cost: $130,000 |
- | - | $93,700 | 6,761 | - | - |
- - kWh |
$93,700 6,761 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,203 Cost: $8,830 |
$3,203 | 37,598 | - | - | - | - |
$3,203 37,598 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $181,168 Cost: $270,700 |
$47,802 | 531,630 | $93,700 | 6,761 | $39,666 | - | $47,802 531,630 kWh |
$93,700 6,761 MMBtu |
$39,666 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $39,666 Cost: - |
- | - | - | - | $39,666 | - | - - kWh |
- - MMBtu |
$39,666 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Natural Gas | One-time Revenue or Avoided Cost |