Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2007 |
Principal Product | Shelving, SOHO Cabinets, Lateral File Cabinet |
NAICS | 337214 - Office Furniture (except Wood) Manufacturing |
SIC | 2522 - Office Furniture, Except Wood |
Sales | $50,000,000-$100,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 88,660 |
Annual Production | 1,718,400 Pieces |
Production Hrs. Annual | 8,500 |
Location (State) | DE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $561,708 | 37,865 | kWh | $14.83 |
Electricity Demand | $73,777 | 876 | kW-months/year | $84.22 |
Natural Gas | $561,708 | 37,865 | MMBtu | $14.83 |
TOTAL ENERGY COSTS | $1,221,593 | |||
RECOMMENDED SAVINGS* | $350,635 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $310,007 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,373 Cost: - |
$5,373 | 40,250 | - | - |
$5,373 40,250 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $167,986 Cost: $65,000 |
- | - | $167,986 | 15,096 |
- - kWh |
$167,986 15,096 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $92,780 Cost: $18,375 |
- | - | $92,780 | 7,844 |
- - kWh |
$92,780 7,844 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS |
Savings: $6,554 Cost: $1,772 |
- | - | $6,554 | 554 |
- - kWh |
$6,554 554 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $24,677 Cost: $10,000 |
- | - | $24,677 | 1,670 |
- - kWh |
$24,677 1,670 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $37,314 Cost: $108,987 |
$37,314 | 357,847 | - | - |
$37,314 357,847 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $15,951 Cost: $80,000 |
$15,951 | 187,480 | - | - |
$15,951 187,480 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $350,635 Cost: $284,134 |
$58,638 | 585,577 | $291,997 | 25,164 | $58,638 585,577 kWh |
$291,997 25,164 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $310,007 Cost: $194,134 |
$42,687 | 398,097 | $267,320 | 23,494 | $42,687 398,097 kWh |
$267,320 23,494 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |