IAC Assessment: DL0071
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DL0071
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Delaware
Assessment Year 2011
Principal Product extruded thermoplastics
NAICS 326113 - Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing
SIC 3089 - Plastics Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 40
Plant Area (Sq.Ft.) 40,000
Annual Production 400,000,000 Pieces
Production Hrs. Annual 4,160
Location (State) DE
View Case Study
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $136,160 1,215,720 kWh $0.11
Electricity Demand $56,024 6,260 kW-months/year $8.95
Electricity Fees $7,182 - $ -
Fuel Oil #2 $5,598 247 MMBtu $22.66
TOTAL ENERGY COSTS $204,964
RECOMMENDED SAVINGS* $28,994 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $22,318
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.2691 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS Savings:
$1,220
Cost:
$600
$1,220 10,900 $1,220
10,900
kWh
02: 2.4235 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES Savings:
$650
Cost:
-
$650 5,820 $650
5,820
kWh
03: 2.7314 REDUCE VENTILATION AIR Savings:
$4,520
Cost:
-
$4,520 40,400 $4,520
40,400
kWh
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,600
Cost:
$5,300
$2,600 23,300 $2,600
23,300
kWh
05: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$1,970
Cost:
$2,390
$1,970 17,600 $1,970
17,600
kWh
06: 2.2511 INSULATE BARE EQUIPMENT Savings:
$430
Cost:
$180
$430 3,800 $430
3,800
kWh
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$710
Cost:
$100
$710 6,300 $710
6,300
kWh
08: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$590
Cost:
$2,484
$590 5,270 $590
5,270
kWh
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,676
Cost:
$1,800
$1,676 15,242 $1,676
15,242
kWh
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$6,668
Cost:
$2,500
$6,668 60,627 $6,668
60,627
kWh
11: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$7,960
Cost:
$4,000
$7,960 71,100 $7,960
71,100
kWh
TOTAL RECOMMENDED Savings:
$28,994
Cost:
$19,354
$28,994 260,359 $28,994
260,359
kWh
TOTAL IMPLEMENTED Savings:
$22,318
Cost:
$9,684
$22,318 200,417 $22,318
200,417
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage