Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2013 |
Principal Product | Wire cloth, metal belting |
NAICS | 332618 - Other Fabricated Wire Product Manufacturing |
SIC | 3496 - Misc. Fabricated Wire Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 346,000 |
Annual Production | 9,999 Units |
Production Hrs. Annual | 6,000 |
Location (State) | MD |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $346,133 | 5,069,553 | kWh | $0.07 |
Electricity Demand | $68,457 | 12,758 | kW-months/year | $5.37 |
LPG | $45,433 | 2,564 | MMBtu | $17.72 |
TOTAL ENERGY COSTS | $460,023 | |||
RECOMMENDED SAVINGS* | $118,501 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | LPG | Electricity Usage | Natural Gas | LPG | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,410 Cost: $2,000 |
$7,410 | 88,223 | - | - | - | - |
$7,410 88,223 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $12,684 Cost: $2,350 |
- | - | - | - | $12,684 | 573 |
- - kWh |
- - MMBtu |
$12,684 573 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $11,278 Cost: $2,350 |
$11,278 | 134,260 | - | - | - | - |
$11,278 134,260 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,080 Cost: $500 |
$2,080 | 24,774 | - | - | - | - |
$2,080 24,774 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,930 Cost: $2,000 |
$5,930 | 70,577 | - | - | - | - |
$5,930 70,577 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1332 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS |
Savings: $27,486 Cost: $11,000 |
- | - | $(-17,948) | (-2,564) | $45,434 | 2,564 |
- - kWh |
$(-17,948) (-2,564) MMBtu |
$45,434 2,564 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $10,394 Cost: $7,600 |
$10,394 | 123,739 | - | - | - | - |
$10,394 123,739 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $100 Cost: $85 |
$100 | 1,190 | - | - | - | - |
$100 1,190 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $41,139 Cost: $70,800 |
$63,840 | 760,000 | $(-22,701) | (-3,243) | - | - |
$63,840 760,000 kWh |
$(-22,701) (-3,243) MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $118,501 Cost: $98,685 |
$101,032 | 1,202,763 | $(-40,649) | (-5,807) | $58,118 | 3,137 | $101,032 1,202,763 kWh |
$(-40,649) (-5,807) MMBtu |
$58,118 3,137 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | LPG | Electricity Usage | Natural Gas | LPG |