Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2013 |
Principal Product | Rigid Plastics |
NAICS | 325211 - Plastics Material and Resin Manufacturing |
SIC | 2821 - Plastics Materials And Resins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 26,600,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | DE |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $966,000 | 13,500,582 | kWh | $0.07 |
Natural Gas | $196,000 | 40,700 | MMBtu | $4.82 |
TOTAL ENERGY COSTS | $1,162,000 | |||
RECOMMENDED SAVINGS* | $116,566 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $58,404 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $13,600 Cost: $800 |
$5,600 | 78,000 | $8,000 | 1,650 |
$5,600 78,000 kWh |
$8,000 1,650 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $27,600 Cost: $16,500 |
$27,600 | 386,000 | - | - |
$27,600 386,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $21,500 Cost: $349,314 |
$21,500 | 300,000 | - | - |
$21,500 300,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $14,300 Cost: $3,000 |
$14,300 | 200,000 | - | - |
$14,300 200,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $5,900 Cost: $300 |
- | - | $5,900 | 1,220 |
- - kWh |
$5,900 1,220 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $6,500 Cost: - |
$6,500 | 96,000 | - | - |
$6,500 96,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $4,362 Cost: $4,680 |
- | - | $4,362 | 905 |
- - kWh |
$4,362 905 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,400 Cost: $330 |
- | - | $2,400 | 510 |
- - kWh |
$2,400 510 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $12,504 Cost: $20,000 |
$12,504 | 174,636 | - | - |
$12,504 174,636 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $3,600 Cost: $1,000 |
$3,600 | 50,200 | - | - |
$3,600 50,200 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $4,300 Cost: $700 |
$4,300 | 69,000 | - | - |
$4,300 69,000 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $116,566 Cost: $396,624 |
$95,904 | 1,353,836 | $20,662 | 4,285 | $95,904 1,353,836 kWh |
$20,662 4,285 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $58,404 Cost: $373,314 |
$58,404 | 820,836 | - | - | $58,404 820,836 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |