Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Delaware |
---|---|
Assessment Year | 2016 |
Principal Product | Mechanical Power Transmission |
NAICS | 336211 - Motor Vehicle Body Manufacturing |
SIC | 3713 - Truck And Bus Bodies |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 9,999 |
Annual Production | 40,000 Units |
Production Hrs. Annual | 8,760 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $117,295 | 846,578 | kWh | $0.14 |
Electricity Demand | $20,119 | 3,030 | kW-months/year | $6.64 |
Electricity Fees | $4,465 | - | $ | - |
Natural Gas | $29,476 | 3,686 | MMBtu | $8.00 |
TOTAL ENERGY COSTS | $171,355 | |||
RECOMMENDED SAVINGS* | $40,843 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,095 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,095 Cost: $1,036 |
- | - | - | - | $1,095 | 143 |
- - kWh |
- - kW-months/year |
$1,095 143 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2492 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR |
Savings: $4,815 Cost: $27,020 |
$(-630) | (-3,910) | $(-70) | (-10) | $5,515 | 720 |
$(-630) (-3,910) kWh |
$(-70) (-10) kW-months/year |
$5,515 720 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $3,496 Cost: $9,820 |
- | - | - | - | $3,496 | 456 |
- - kWh |
- - kW-months/year |
$3,496 456 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $1,310 Cost: $2,990 |
- | - | - | - | $1,310 | 171 |
- - kWh |
- - kW-months/year |
$1,310 171 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7264 INTERLOCK HEATING AND AIR CONDITIONING SYSTEMS TO PREVENT SIMULTANEOUS OPERATION |
Savings: $18,930 Cost: $4,739 |
$14,354 | 103,266 | $1,673 | 252 | $2,903 | 379 |
$14,354 103,266 kWh |
$1,673 252 kW-months/year |
$2,903 379 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7131 ADD AREA LIGHTING SWITCHES |
Savings: $1,520 Cost: $910 |
$1,490 | 10,740 | $30 | 5 | - | - |
$1,490 10,740 kWh |
$30 5 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,810 Cost: $35,710 |
$5,750 | 41,360 | $60 | 9 | - | - |
$5,750 41,360 kWh |
$60 9 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,400 Cost: $3,900 |
$2,400 | 17,273 | - | - | - | - |
$2,400 17,273 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $1,467 Cost: $565 |
$1,467 | 10,559 | - | - | - | - |
$1,467 10,559 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,843 Cost: $86,690 |
$24,831 | 179,288 | $1,693 | 255 | $14,319 | 1,869 | $24,831 179,288 kWh |
$1,693 255 kW-months/year |
$14,319 1,869 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,095 Cost: $1,036 |
- | - | - | - | $1,095 | 143 | - - kWh |
- - kW-months/year |
$1,095 143 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |