Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | South Dakota State |
---|---|
Assessment Year | 1997 |
Principal Product | Specialized Tools and Heavy Equipment |
NAICS | n/a |
SIC | 3499 - Fabricated Metal Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 700 |
Plant Area (Sq.Ft.) | 316,343 |
Annual Production | 1,500,000 Pieces |
Production Hrs. Annual | 5,200 |
Location (State) | MN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $233,235 | 9,587,632 | kWh | $0.02 |
Electricity Demand | $277,614 | 23,400 | kW-months/year | $11.86 |
Electricity Fees | $14,154 | - | $ | - |
Natural Gas | $112,121 | 50,254 | MMBtu | $2.23 |
LPG | $43,351 | 7,576 | MMBtu | $5.72 |
TOTAL ENERGY COSTS | $681,440 | |||
RECOMMENDED SAVINGS* | $55,209 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $49,882 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,969 Cost: $44,572 |
$7,558 | 315,064 | $8,411 | 709 | - | - | - | - | - | - | - | - | - | - | - | - |
$7,558 315,064 kWh |
$8,411 709 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,402 Cost: $1,260 |
$719 | 29,894 | $683 | 58 | - | - | - | - | - | - | - | - | - | - | - | - |
$719 29,894 kWh |
$683 58 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,060 Cost: $1,230 |
- | - | - | - | $2,060 | 924 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,060 924 MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4151 MINIMIZE WATER USAGE |
Savings: $2,363 Cost: $2,200 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | $2,363 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
$2,363 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE |
Savings: $1,373 Cost: $1,500 |
$(-48) | (-2,052) | $(-534) | (-48) | - | - | $371 | 528 | - | - | - | - | $1,584 | - | - | - |
$(-48) (-2,052) kWh |
$(-534) (-48) kW-months/year |
- - MMBtu |
$371 528 gal |
- - $ |
- - $ |
$1,584 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.1175 USE A DIFFERENT OR RECYCLED RAW MATERIAL |
Savings: $2,552 Cost: - |
- | - | - | - | - | - | - | - | - | - | $2,552 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
$2,552 - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.515 INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE |
Savings: $29,490 Cost: $10,700 |
- | - | - | - | - | - | - | - | $29,490 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$29,490 - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $55,209 Cost: $61,462 |
$8,229 | 342,906 | $8,560 | 719 | $2,060 | 924 | $371 | 528 | $29,490 | - | $2,552 | - | $1,584 | - | $2,363 | - | $8,229 342,906 kWh |
$8,560 719 kW-months/year |
$2,060 924 MMBtu |
$371 528 gal |
$29,490 - $ |
$2,552 - $ |
$1,584 - $ |
$2,363 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $49,882 Cost: $58,702 |
$7,558 | 315,064 | $8,411 | 709 | $2,060 | 924 | - | - | $29,490 | - | - | - | - | - | $2,363 | - | $7,558 315,064 kWh |
$8,411 709 kW-months/year |
$2,060 924 MMBtu |
- - gal |
$29,490 - $ |
- - $ |
- - $ |
$2,363 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption |