IAC Assessment: DS0107
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DS0107
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center South Dakota State
Assessment Year 1998
Principal Product Custom Molds
NAICS n/a
SIC 3544 - Special Dies, Tools, Jigs & Fixtures
Sales $1,000,000-$5,000,000
# of Employees 25
Plant Area (Sq.Ft.) 20,440
Annual Production 230 Pieces
Production Hrs. Annual 2,990
Location (State) MN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $11,637 375,440 kWh $0.03
Electricity Demand $9,368 1,212 kW-months/year $7.73
Electricity Fees $4,400 - $ -
Natural Gas $4,683 729 MMBtu $6.42
TOTAL ENERGY COSTS $32,571
RECOMMENDED SAVINGS* $6,678 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,286
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,583
Cost:
$6,257
$842 27,257 $741 96 - - - - $842
27,257
kWh
$741
96
kW-months/year
-
-
MMBtu
-
-
$
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$686
Cost:
$600
- - - - $686 107 - - -
-
kWh
-
-
kW-months/year
$686
107
MMBtu
-
-
$
03: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$250
Cost:
$150
- - - - - - $250 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$250
-
$
04: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE Savings:
$1,873
Cost:
$90
- - - - - - $1,873 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,873
-
$
05: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$2,286
Cost:
$240
- - - - - - $2,286 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$2,286
-
$
TOTAL RECOMMENDED Savings:
$6,678
Cost:
$7,337
$842 27,257 $741 96 $686 107 $4,409 - $842
27,257
kWh
$741
96
kW-months/year
$686
107
MMBtu
$4,409
-
$
TOTAL IMPLEMENTED Savings:
$2,286
Cost:
$240
- - - - - - $2,286 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$2,286
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes