IAC logo
IAC Assessment: DS0109
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DS0109
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center South Dakota State
Assessment Year 1998
Principal Product Cheese and Whey
NAICS n/a
SIC 2022 - Cheese, Natural And Processed
Sales $50,000,000-$100,000,000
# of Employees 170
Plant Area (Sq.Ft.) 200,000
Annual Production 65,120,000 Pounds
Production Hrs. Annual 8,736
Location (State) MN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $494,769 17,177,023 kWh $0.03
Electricity Demand $180,778 26,976 kW-months/year $6.70
Electricity Fees $2,642 - $ -
Natural Gas $709,996 261,306 MMBtu $2.72
TOTAL ENERGY COSTS $2,040,019
RECOMMENDED SAVINGS* $424,398 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $417,297
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,776
Cost:
$13,369
$2,699 93,200 $1,077 161 - - - - - - - - $2,699
93,200
kWh
$1,077
161
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,907
Cost:
$1,500
$1,203 41,618 $704 105 - - - - - - - - $1,203
41,618
kWh
$704
105
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
03: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS Savings:
$10,041
Cost:
$13,000
- - - - $10,041 3,719 - - - - - - -
-
kWh
-
-
kW-months/year
$10,041
3,719
MMBtu
-
-
lb
-
-
$
-
-
$
04: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$250
Cost:
$250
- - - - - - - - - - $250 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
$250
-
$
05: 4.114 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS Savings:
$4,740
Cost:
$1,500
- - - - - - $4,740 25,020 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$4,740
25,020
lb
-
-
$
-
-
$
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$3,325
Cost:
$50
- - - - - - $3,325 20,000 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$3,325
20,000
lb
-
-
$
-
-
$
07: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT Savings:
$400,359
Cost:
$200,000
$(-661) (-22,860) $(-420) (-63) - - - - $401,440 - - - $(-661)
(-22,860)
kWh
$(-420)
(-63)
kW-months/year
-
-
MMBtu
-
-
lb
$401,440
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$424,398
Cost:
$229,669
$3,241 111,958 $1,361 203 $10,041 3,719 $8,065 45,020 $401,440 - $250 - $3,241
111,958
kWh
$1,361
203
kW-months/year
$10,041
3,719
MMBtu
$8,065
45,020
lb
$401,440
-
$
$250
-
$
TOTAL IMPLEMENTED Savings:
$417,297
Cost:
$216,250
$542 18,758 $284 42 $10,041 3,719 $4,740 25,020 $401,440 - $250 - $542
18,758
kWh
$284
42
kW-months/year
$10,041
3,719
MMBtu
$4,740
25,020
lb
$401,440
-
$
$250
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Administrative Changes