IAC Assessment: DS0167
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: DS0167
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center South Dakota State
Assessment Year 2000
Principal Product Air Moving Equipment
NAICS n/a
SIC 3564 - Blowers And Fans
Sales $10,000,000-$50,000,000
# of Employees 160
Plant Area (Sq.Ft.) 150,000
Annual Production 8,400 Pieces
Production Hrs. Annual 3,536
Location (State) SD
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $71,789 2,179,660 kWh $0.03
Electricity Demand $39,173 5,640 kW-months/year $6.95
Electricity Fees $6,656 - $ -
Natural Gas $65,870 15,767 MMBtu $4.18
LPG $11,598 629 MMBtu $18.44
TOTAL ENERGY COSTS $201,518
RECOMMENDED SAVINGS* $20,707 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Personnel Changes Primary Raw Material Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Personnel Changes Primary Raw Material Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $ $ $ $ $
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$2,633
Cost:
$850
- - - - $2,633 630 - - - - - - - - -
-
kWh
-
-
kW-months/year
$2,633
630
MMBtu
-
-
gal
-
-
$
-
-
$
-
-
$
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,120
Cost:
$540
$653 19,930 $467 67 - - - - - - - - - - $653
19,930
kWh
$467
67
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,204
Cost:
$3,793
$670 20,223 $534 77 - - - - - - - - - - $670
20,223
kWh
$534
77
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
-
-
$
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$257
Cost:
$216
$257 7,913 - - - - - - - - - - - - $257
7,913
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
-
-
$
05: 3.2121 CONVERT TO ELECTROSTATIC POWDER COATING Savings:
$12,389
Cost:
$35,000
- - - - - - - - - - $12,389 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
$12,389
-
$
-
-
$
06: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE Savings:
$3,104
Cost:
$4,075
- - $(-200) (-29) - - $1,767 589 $(-2,080) - - - $3,617 - -
-
kWh
$(-200)
(-29)
kW-months/year
-
-
MMBtu
$1,767
589
gal
$(-2,080)
-
$
-
-
$
$3,617
-
$
TOTAL RECOMMENDED Savings:
$20,707
Cost:
$44,474
$1,580 48,066 $801 115 $2,633 630 $1,767 589 $(-2,080) - $12,389 - $3,617 - $1,580
48,066
kWh
$801
115
kW-months/year
$2,633
630
MMBtu
$1,767
589
gal
$(-2,080)
-
$
$12,389
-
$
$3,617
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Personnel Changes Primary Raw Material Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Personnel Changes Primary Raw Material Ancillary Material Cost